vers.;v4.23;Abort Procedure;;3;mrl;mcc;rdh;time
vers.;v4.27;Abort Procedure;;3;mrl;mcc;rdh;time
0:00;MCC;BEGIN SEQUENCE: Defueling Rocket;Defueling;3;;;;
0:00;MCC;Inform OPS of Launch Abort;;3;;;;
0:00;EGSE;Confirm all valve switches are in OFF position (Except OxDV & HPDV);;3;;;;
......@@ -18,8 +18,12 @@ vers.;v4.23;Abort Procedure;;3;mrl;mcc;rdh;time
0:00;OBDH;Deactivate Heizi;;3;;;;
0:00;ALL;Wait for Launchpad to be clear of N2O fumes depending on OxMass before Defueling;;3;;;;
0:00;MCC;BEGIN SEQUENCE: Ground support equipment passivation;GSE Passivation;3;;;;
0:00;EGSE;Turn ON EPS_BAT (Rocket OFF);;2;;;;
0:00;MCC;Announce BEGIN of Radio Silence;;3;;;;
0:00;MRL;Go to MRL, Close N2O Bottle 1 & N2O Bottle 2, THEN...;;2;;;;
0:00;MRL;Go to MRL, THEN...;;2;;;;
0:00;MRL;Remove HP section maintenance cover, THEN...;;2;;;;
0:00;MRL;Open RMDV & Step Back, Wait until NCE-Tank is pressureless, THEN...;;2;;;;
0:00;MRL;Close N2O Bottle 1 & N2O Bottle 2, THEN...;;2;;;;
0:00;MRL;RETURN to Block House;;2;;;;
0:00;EGSE;Open OxDV;;2;;;;
0:00;EGSE;Open OxV1;;2;;;;
......
vers.;v4.23;Launch Procedure;;0;MRL;MCC;RdHill;Time per step
vers.;v4.27;Launch Procedure;;0;MRL;MCC;RdHill;Time per step
147:20;MCC;BEGIN SEQUENCE: Power on EGSE;Power on EGSE;1;;;;
147:20;WIND;Start wind weighting analysis;;1;;;;
147:20;EGSE;Check CLD connection;;1;;;;
......@@ -117,7 +117,6 @@ vers.;v4.23;Launch Procedure;;0;MRL;MCC;RdHill;Time per step
110:00;MCC;BEGIN SEQUENCE: Ground segment pressure test (PHASE YELLOW) ;GSE Pressure Test;2;LuF, AlS, LeD: 1x Helm, 3x Ear protectors;ChB, FiH, JuL, LiA, MiS;;
130:50;EGSE/ MRL;Check Bottle Temperatures @ OxT1, OxT2, HPT2. If above 30C aknowledge high temperature. If above 35C enter HOLD;;2;;;;00:10
130:40;EGSE/ MRL;Check Water Temperatures @ OxWT1, OxWT2, HPWT2;;2;;;;00:10
110:00;MRL;Confirm that all hatches are closed;;2;;;;01:00
109:00;MRL;Confirm He bottle 1 connector is attached;;2;;;;
109:00;MRL;Confirm He bottle 2 connector is attached;;2;;;;
109:00;MRL;Confirm N2O bottle 1 connector is attached;;2;;;;
......@@ -150,10 +149,10 @@ vers.;v4.23;Launch Procedure;;0;MRL;MCC;RdHill;Time per step
105:00;EGSE/ MRL;Open & Close MPV3 SHORTLY;;2;;;;
0:00;MRL;Open HPNV1 completely;;2;;;;
0:00;MRL;Step Back;;2;;;;
0:00;EGSE;"Open & Close HPV1 STEPWISE untile HPLPT equal to HPPT1 and check for leakage @HPLPT (If leakage occurs continue with ""GSE Passivation Procedure"")";;2;;;;
0:00;EGSE;"Confirm RHPPT & RoxTPT 1 Bar (on Pressure continue with ""Rocket Passivation Procedure"")";;2;;;;
0:00;EGSE;"Open & Close HPV1 STEPWISE untile HPLPT equal to HPPT1 and check for leakage @HPLPT (If leakage occurs proceed to passivation Procedure out of sequence)";;2;;;;
0:00;EGSE;"Confirm RHPPT & RoxTPT 1 Bar (If pressure is higher proceed to passivation Procedure out of sequence);;2;;;;
0:00;EGSE;Open HPV1;;2;;;;
0:00;EGSE;"Open & Close HPV2 STEPWISE untile HPPT2 equal to HPLPT and check for leakage @HPPT2 (If leakage occurs continue with ""GSE Passivation Procedure"")";;2;;;;
0:00;EGSE;"Open & Close HPV2 STEPWISE untile HPPT2 equal to HPLPT and check for leakage @HPPT2 (If leakage occurs proceed to passivation Procedure out of sequence)";;2;;;;
0:00;EGSE;Close HPV1;;2;;;;
0:00;EGSE;Open HPDV & confirm HPLPT 0 Bar;;2;;;;
0:00;EGSE;Open HPV2 & confirm HPPT2 0 Bar;;2;;;;
......@@ -163,7 +162,7 @@ vers.;v4.23;Launch Procedure;;0;MRL;MCC;RdHill;Time per step
87:10;EGSE;Confirm MPV1/2 closed;;2;;;;
87:10;EGSE;Open OxDV;;2;;;;
87:10;EGSE;Open & Close STEPWISE MPV3 to 0 Bar @OxOutPT;;2;;;;
87:10;EGSE;Check OxInPT1 and OxInPT2 for leakage (If leakage occurs proceed to GSE passivation Procedure);;2;;;;
87:10;EGSE;Check OxInPT1 and OxInPT2 for leakage (If leakage occurs proceed to passivation Procedure out of sequence);;2;;;;
87:10;EGSE;Confirm MPV3 closed;;2;;;;
87:10;EGSE;Open & Close STEPWISE OxV1 to 0 Bar @OxInPT1;;2;;;;
87:10;EGSE;Open & Close STEPWISE OxV2 to 0 Bar @OxInPT2;;2;;;;
......@@ -174,12 +173,10 @@ vers.;v4.23;Launch Procedure;;0;MRL;MCC;RdHill;Time per step
103:30;EGSE;Decouple Helium coupling;;2;;;;00:20
103:10;EGSE;Move arm away from rocket;;2;;;;
103:10;EGSE;Move arm to rocket;;2;;;;01:00
102:10;MRL;Close He Bottle 1 and check HPSM for leakage (If leakage occurs continue with Passivation Procedure);;2;;;;01:00
102:10;MRL;Close He Bottle 1 and check HPSM for leakage (If leakage occurs proceed to passivation Procedure out of sequence);;2;;;;01:00
101:10;MRL;Open MBV;;2;;;;
101:10;EGSE/ MRL;Check and compare pressure HPPT1 with HPPG1 0 Bar;;2;;;;
101:10;MRL;Close MBV;;2;;;;00:30
100:40;MRL;Open RMDV & relief pressure;;2;;;;
100:40;MRL;Close RMDV;;2;;;;
100:40;MRL;Safety is ensured;;2;;;;
100:40;MCC;EGSE @MRL to MRL;;1;;;;
100:40;EGSE;Switch OFF N20 coupling;;1;;;;
......@@ -200,24 +197,31 @@ vers.;v4.23;Launch Procedure;;0;MRL;MCC;RdHill;Time per step
130:50;EGSE/ MRL;Check Bottle Temperatures @ OxT1, OxT2, HPT2. If above 30C aknowledge high temperature. If above 35C enter HOLD;;1;;;;00:10
130:40;EGSE/ MRL;Check Water Temperatures @ OxWT1, OxWT2, HPWT2;;1;;;;00:10
99:20;MRL;BEGIN SEQUENCE: Prime Rocket;Prime Rocket;2;;;;
99:20;EGSE;Turn ON EPS_BAT;;2;;;;01:00
99:40;OBDH;Check RDV;;2;;;;00:10
99:30;OBDH;Check RNCEV;;2;;;;00:10
99:20;OBDH;Check RMOxOV;;2;;;;00:10
99:10;OBDH;Check RMOxSV;;2;;;;00:10
99:00;OBDH;Disable RNCEV;;2;;;;00:10
99:20;EGSE;Turn ON EPS_BAT (Rocket OFF);;2;;;;01:00
99:20;MRL;Confirm working personel is grounded;;2;;;;01:00
99:20;MRL;Confirm all spring retracted hatches are moving freely;;2;;;;
99:20;MRL;Confirm that RMDV is closed;;2;;;;01:00
99:00;MRL;Close & secure HP maintenance cover;;2;;;;01:00
99:00;MRL;Close & secure MainOX maintenance cover;;2;;;;01:00
98:50;MRL;Turn on GoPro Camera at end of Launch Rail;;2;;;;00:20
99:20;MRL;Connect Ignition Umbilical;;2;;;;00:30
98:30;MRL;Insert all EPS Bridges;;2;;;;03:00
95:30;MRL;Confirm Bridge Hatch is Secured;;2;;;;00:20
95:30;MRL;Close bridge maintenance cover;;2;;;;00:20
99:20;MRL;Confirm spring retracted cover at He coupling is moving freely;;2;;;;
99:20;MRL;Confirm spring retracted cover at N2O coupling is moving freely;;2;;;;
95:00;MRL;Confirm that HP maintenance cover is closed & secured;;2;;;;01:00
95:30;MRL;Confirm bridge maintenance cover is closed & secured;;2;;;;00:20
95:00;MRL;Confirm that MainOX maintenance cover is closed & secured;;2;;;;01:00
95:10;EGSE @MRL;return to MCC;;2;;;;
95:10;OPS;Elevate MRL to 90 degrees;;2;;;;05:00
89:40;EGSE;Zero OxTank Mass;;2;;;;01:00
88:40;MCC;BEGIN SEQUENCE: Fueling Preparations (PHASE YELLOW);Fueling Preparations;2;;;;
130:50;EGSE/ MRL;Check Bottle Temperatures @ OxT1, OxT2, HPT2. If above 30C aknowledge high temperature. If above 35C enter HOLD;;2;;;;00:10
130:40;EGSE/ MRL;Check Water Temperatures @ OxWT1, OxWT2, HPWT2;;2;;;;00:10
127:40;OBDH;!!!Check RDV;;2;;;;00:10
127:30;OBDH;!!!Check RNCEV;;2;;;;00:10
127:20;OBDH;!!!Check RMOxOV;;2;;;;00:10
127:10;OBDH;!!!Check RMOxSV;;2;;;;00:10
127:00;OBDH;!!!Disable RNCEV;;2;;;;00:10
88:40;MRL;Put on safety equipment;;2;;;;00:30
10:10;MRL;Confirm HPNV1 is Open;;2;;;;
10:10;MRL;Confirm HPNV2 is Closed;;2;;;;
......@@ -369,7 +373,8 @@ vers.;v4.23;Launch Procedure;;0;MRL;MCC;RdHill;Time per step
0:00;MCC;BEGIN SEQUENCE: PASSIVATION (PHASE YELLOW);Passivation;2;;;;
68:40;MCC;Announce BEGIN of Radio Silence;;2;;;;
0:00;MCC;Turn audio volume up;;2;;;;
0:00;MRL;Go to MRL, Close N2O Bottle 1 & N2O Bottle 2, THEN...;;2;;;;
0:00;MRL;Go to MRL, THEN...;;2;;;;
0:00;MRL;Close N2O Bottle 1 & N2O Bottle 2, THEN...;;2;;;;
0:00;MRL;RETURN to Block House;;2;;;;
0:00;EGSE;Open OxDV;;2;;;;
0:00;EGSE;Open OxV1;;2;;;;
......
vers.;v4.23;Passivation out of sequence Procedure;;2;mrl;mcc;rdh;time
vers.;v4.27;Passivation out of sequence Procedure;;2;mrl;mcc;rdh;time
0:00;MCC;BEGIN SEQUENCE: Prepare Passivation Sequence;Prepare Passivation;2;;;;
0:00;MCC/MRL;Recall and make sure BOTH N2O Bottles & He Bottle 2 are still closed! Else continue with Abort Procedure;;2;;;;
0:00;MCC;Inform OPS of Passivation out of sequence;;2;;;;
......