Renamed Pressure tests to pneumatic pressure test and fuling preparations

This commit is contained in:
Finn 2020-05-26 16:09:15 +02:00
parent fda451a3ac
commit 041b7ff333
1 changed files with 21 additions and 20 deletions

View File

@ -1,4 +1,4 @@
vers.;v4.1;Launch Procedure;;0;MRL;MCC;RdHill;Time per step;
vers.;v4.2;Launch Procedure;;0;MRL;MCC;RdHill;Time per step;
147:20;EGSE;BEGIN of Power on EGSE Sequence;Power on EGSE;1;;;;;
147:20;EGSE;Check CLD connection;;1;;;;;
147:20;EGSE;Switch on CLD via Battery & check voltage (24 Volt);;1;;;;;
@ -106,7 +106,7 @@ vers.;v4.1;Launch Procedure;;0;MRL;MCC;RdHill;Time per step;
113:00;EGSE;Turn off Ignition Secure;;1;;;;;
113:00;EGSE@MRL;Remove Bridges B1 and B2;;1;;;;;
113:00;MRL;Remove Ignition test Receptical;;1;;;;03:00;
110:00;MCC;Ground Segment Pressure Test (PHASE YELLOW) ;Ground Pressure Test;1;;;;;
110:00;MCC;BEGIN pneumatic pressure test (PHASE YELLOW) ;Pneumatic Pressure Test;1;;;;;
110:00;MRL;Confirm that all hatches are closed;;1;;;;01:00;
109:00;MRL;Check HE bottle 1 connector is attached;;1;;;;;
109:00;MRL;Check HE bottle 2 connector is attached;;1;;;;;
@ -118,6 +118,7 @@ vers.;v4.1;Launch Procedure;;0;MRL;MCC;RdHill;Time per step;
109:00;MRL;Check Pneumatik hose is connected on both ends;;1;;;;02:00;
107:00;MRL;Put on safety equipment;;2;;;;;
107:00;MRL;Move into Position to open HE Bottle 1;;2;;;;;
107:00;MRL;Confirm MBV is closed;;2;;;;;
107:00;EGSE;Confirm if HPV1 is closed;;2;;;;;
107:00;EGSE;Confirm MPV1/2 is closed;;2;;;;;
107:00;MRL;Open HE Bottle 1;;2;;;;01:00;
@ -126,9 +127,9 @@ vers.;v4.1;Launch Procedure;;0;MRL;MCC;RdHill;Time per step;
106:00;MRL;Check Harris PPR (50 to 8 bar);;2;;;;;
106:00;MRL;Check pneumatic PPG (8 bar);;2;;;;;
106:00;MRL;Step back;;2;;;;01:00;
105:00;EGSE/MRL;Open & Close HPV1 SHORTLY & Check HPPT1;;2;;;;;
105:00;EGSE;Confirm HPPT1 is at 300 Bar;;2;;;;;
105:00;EGSE;Confirm HPLPT less than 10 Bar;;2;;;;;
105:00;EGSE/MRL;Open & Close HPV1 SHORTLY & Check HPPT1;;2;;;;;
105:00;EGSE/MRL;Open & Close HPV2 SHORTLY & Check HPPT2 0 bar;;2;;;;;
105:00;EGSE/MRL;Open & Close HPDV SHORTLY & Check HPLPT 0 bar;;2;;;;;
105:00;EGSE/MRL;Open & Close OxV1 SHORTLY;;2;;;;;
@ -149,13 +150,13 @@ vers.;v4.1;Launch Procedure;;0;MRL;MCC;RdHill;Time per step;
100:40;MCC;MiS to MRL;;1;;;;;
100:40;EGSE;Switch off N20 coupling;;1;;;;;
100:40;EGSE;Switch off HE coupling;;1;;;;;
100:40;MRL;Release Pneumatic lines;;1;;;;00:20;
100:20;EGSE;Confirm Fueling arm is off;;1;;;;;
100:40;MRL;Release Pneumatic lines of couplings;;1;;;;00:20;
100:20;EGSE;Confirm Fueling arm is switched off;;1;;;;;
100:20;EGSE;Check OxOutPT and HPLPT 0 bar;;1;;;;;
100:20;MRL;Couple Helium coupling;;1;;;;00:30;
99:50;MRL;Couple N2O coupling;;1;;;;00:30;
99:20;MRL;HOLD / RESTART;;1;;;;;
99:20;MRL;BEGIN Arming Rocket SEQUENCE Part 1;Arming 1;1;;;;;
99:20;MRL;BEGIN Arming Rocket Part 1;Arming Pt.1;1;;;;;
99:20;MRL;Connect Ignition Umbilical;;1;;;;00:30;
98:50;MRL;Turn on GoPro Camera at end of Launch Rail;;1;;;;00:20;
98:30;MRL;Insert EPS Bridges;;1;;;;03:00;
@ -164,11 +165,11 @@ vers.;v4.1;Launch Procedure;;0;MRL;MCC;RdHill;Time per step;
95:10;OPS;Elevate MRL to 90 degrees;;1;;;;05:00;
90:10;EGSE;Powercycle EPS to to start flight mode on Telemega;;1;;;;00:30;
89:40;EGSE;Calibrate loadcell (Set to 0);;1;;;;01:00;
88:40;MCC;BEGIN Pressure Test Flight Segment (PHASE YELLOW) ;Pressure Test Rocket;2;;;;;
88:40;MCC;BEGIN Fuling Preparations (PHASE YELLOW) ;Fuling Preparations;2;;;;;
88:40;MRL;Put on safety equipment;;2;;;;00:30;
88:10;MRL;Open HE Bottle 1;;2;;;;01:00;
88:10;MRL;Open He Bottle 1;;2;;;;01:00;
87:10;MRL;Step back;;2;;;;;
87:10;EGSE;Open & Close stepwise MPV1/MPV2 to 50 Bar @ OxInPT1 & OxInPT2;;2;;;;;
87:10;EGSE;Open & Close STEPWISE MPV1/MPV2 to 50 Bar @ OxInPT1 & OxInPT2;;2;;;;;
87:10;MRL;Check & compare OxInPT1 with OxInPG1 based on Bottle temperature (max 50 bar);;2;;;;;
87:10;MRL;Check & compare pressure OxInPT2 with OxInPG2 based on Bottle temperature (max 50 bar);;2;;;;;
87:10;MRL;Check Temperature of N2O Bottle 1 @OxT1 & OxWT1 (max 22C);;2;;;;;
@ -193,28 +194,28 @@ vers.;v4.1;Launch Procedure;;0;MRL;MCC;RdHill;Time per step;
125:50;OBDH;Test Connection to STX3;;1;;;;00:20;
125:30;OBDH;Confirm that STX3 Package received by email;;1;;;;00:30;
68:40;OBDH;Acknowledge start of Fueling;;3;;;;01:00;CHANGE to 3 steps
67:40;EGSE;Open & Close HPV1 to 50 Bar @ ROxTPT (stop at 30 bar and wait 30 seconds to check for leakage);;3;;;;;
67:40;EGSE;Open & Close HPV1 to more than 50 Bar @ RHPPT and check ROxTPT 50 Bar;;3;;;;;
67:40;EGSE;Open & Close HPV1 STEPWISE to 50 Bar @ ROxTPT (stop at 30 bar and wait 30 seconds to check for leakage);;3;;;;;
67:40;EGSE;Open & Close HPV1 STEPWISE to more than 50 Bar @ RHPPT and check ROxTPT 50 Bar;;3;;;;;
67:40;EGSE;Check if HPV1 is closed;;3;;;;;
67:40;OBDH;Open RDV shortly, to check tightness @ RHPPT & ROxTPT (If leakages occur Abort);;3;;;;;
67:40;OBDH;Open RDV SHORTLY, to check tightness @ RHPPT & ROxTPT (If leakages occur Abort);;3;;;;;
67:40;EGSE;Open MPV1/MPV2;;3;;;;;
67:40;EGSE;Open & Close stepwise MPV3 to 50 Bar @ OxOutPT;;3;;;;;
67:40;EGSE;Open & Close MPV3 STEPWISE to 50 Bar @ OxOutPT;;3;;;;;
67:40;EGSE;Close MPV1/MPV2;;3;;;;;
67:40;EGSE;Check & compare OxOutPT with OxInPT1;;3;;;;;
67:40;EGSE;Check if RHPPT & ROxTPT more than OxInPT1, If less Open & Close HPV1;;3;;;;;
67:40;EGSE;Zero OxTank Mass;;3;;;;;
67:40;MCC;Write down Time;;3;;;;;
67:40;EGSE;Open OxV1 ;;3;;;;04:00;
63:40;OBDH;Open stepwise RDV until N2O bottle empty or 25kg OxTankMass, keep temperatures RDVT and RDVET above 10°C and Check delta ROxTPT and OxInPT1;;3;;;;30:00:00;
63:40;OBDH;Open & Close RDV STEPWISE until N2O bottle empty or 25kg OxTankMass, keep temperatures RDVT and RDVET above 10°C and Check delta ROxTPT and OxInPT1;;3;;;;30:00:00;
33:40;EGSE;Close OxV1;;3;;;;00:10;
33:30;EGSE;Check if Pressure rises in OxPT1, if Pressure rises relief via OxV1 or wait for Pressure relief valve;;3;;;;01:00;
32:30;EGSE;Check & compare OxOutPT with OxInPT2;;3;;;;;
32:30;EGSE;Check & compare RHPPT & ROxTPT 50 Bar and more than OxInPT2, If less Open & Close HPV1;;3;;;;;
32:30;EGSE;Open OxV2 ;;3;;;;;
32:30;OBDH;Open stepwise RDV to 25kg OxTankMass, keep temperatures RDVT and RDVET above 10°C and Check delta OxTPT and OxInPT1;;3;;;;20:00;
32:30;OBDH;Open & Close RDV STEPWISE to 25kg OxTankMass, keep temperatures RDVT and RDVET above 10°C and Check delta OxTPT and OxInPT1;;3;;;;20:00;
12:30;EGSE;Close OxV2 ;;3;;;;00:10;
12:20;EGSE;Check if Pressure rises in OxPT2, if Pressure rises relief via OxV2 or wait for Pressure relief valve;;3;;;;01:00;
11:20;EGSE;Open stepwise OxDV until OxOutPT 0 Bar;;3;;;;;
11:20;EGSE;Open OxDV STEPWISE until OxOutPT 0 Bar;;3;;;;;
11:20;OBDH;Check ROxCV for tightness @ ROxTPT;;3;;;;;
11:20;EGSE;Close OxDV;;3;;;;01:00;
10:20;EGSE;Write down OxTankMass;;3;;;;;
@ -244,9 +245,9 @@ vers.;v4.1;Launch Procedure;;0;MRL;MCC;RdHill;Time per step;
6:30;PYL;Confirm Payload is running;;3;;;;00:20;
6:10;AVC;Check if videorecording @ MCC is running;;3;;;;00:05;
6:05;MCC;High Pressure Fuling;HP Fueling;3;;;;;
6:05;EGSE;Open and close HPV1 stepwise until RHPPT 300 Bar or pressure equal to HE Bottle 1;;3;;;;;
6:05;EGSE;Open and close HPV2 stepwise until RHPPT 300 Bar ;;3;;;;;
6:05;EGSE;Open and close HPDV stepwise until HPLPT 0 Bar ;;3;;;;;
6:05;EGSE;Open & Close HPV1 STEPWISE until RHPPT 300 Bar or pressure equal to HE Bottle 1;;3;;;;;
6:05;EGSE;Open & Close HPV2 STEPWISE until RHPPT 300 Bar ;;3;;;;;
6:05;EGSE;Open & close HPDV STEPWISE until HPLPT 0 Bar ;;3;;;;;
6:05;EGSE;Check HPDV closed;;3;;;;;
6:05;OBDH/EGSE;Check for leakage HPLPT 0 Bar & RHPPT 300 Bar ;;3;;;;02:00;
4:05;OBDH;Acknowledge end of Fueling;;3;;;;00:10;
@ -278,7 +279,7 @@ vers.;v4.1;Launch Procedure;;0;MRL;MCC;RdHill;Time per step;
0:00;OBDH;T+600: Verify (Landed);;4;;;;;
0:00;MCC;START OF PASSIVATION (PHASE YELLOW) (Write down Time);Passivation;2;;;;;
0:00;MCC;Turn audio volume up;;2;;;;;
0:00;TMTC;Check ROxTPT & RHPPT 1 Bar, if more: Open & Close stepwise RDV;;2;;;;;
0:00;TMTC;Check ROxTPT & RHPPT 1 Bar, if more: Open & Close STEPWISE RDV;;2;;;;;
0:00;MRL;Go to Testrig, Close N2O Bottle 1 & N2O Bottle 2 then RETURN to Block House;;2;;;;;
0:00;EGSE;Open OxDV;;2;;;;;
0:00;EGSE;Open OxV1;;2;;;;;

1 vers. v4.1 v4.2 Launch Procedure 0 MRL MCC RdHill Time per step
2 147:20 EGSE BEGIN of Power on EGSE Sequence Power on EGSE 1
3 147:20 EGSE Check CLD connection 1
4 147:20 EGSE Switch on CLD via Battery & check voltage (24 Volt) 1
106 113:00 EGSE Turn off Ignition Secure 1
107 113:00 EGSE@MRL Remove Bridges B1 and B2 1
108 113:00 MRL Remove Ignition test Receptical 1 03:00
109 110:00 MCC Ground Segment Pressure Test (PHASE YELLOW) BEGIN pneumatic pressure test (PHASE YELLOW) Ground Pressure Test Pneumatic Pressure Test 1
110 110:00 MRL Confirm that all hatches are closed 1 01:00
111 109:00 MRL Check HE bottle 1 connector is attached 1
112 109:00 MRL Check HE bottle 2 connector is attached 1
118 109:00 MRL Check Pneumatik hose is connected on both ends 1 02:00
119 107:00 MRL Put on safety equipment 2
120 107:00 MRL Move into Position to open HE Bottle 1 2
121 107:00 MRL Confirm MBV is closed 2
122 107:00 EGSE Confirm if HPV1 is closed 2
123 107:00 EGSE Confirm MPV1/2 is closed 2
124 107:00 MRL Open HE Bottle 1 2 01:00
127 106:00 MRL Check Harris PPR (50 to 8 bar) 2
128 106:00 MRL Check pneumatic PPG (8 bar) 2
129 106:00 MRL Step back 2 01:00
130 105:00 EGSE/MRL Open & Close HPV1 SHORTLY & Check HPPT1 2
131 105:00 EGSE Confirm HPPT1 is at 300 Bar 2
132 105:00 EGSE Confirm HPLPT less than 10 Bar 2
105:00 EGSE/MRL Open & Close HPV1 SHORTLY & Check HPPT1 2
133 105:00 EGSE/MRL Open & Close HPV2 SHORTLY & Check HPPT2 0 bar 2
134 105:00 EGSE/MRL Open & Close HPDV SHORTLY & Check HPLPT 0 bar 2
135 105:00 EGSE/MRL Open & Close OxV1 SHORTLY 2
150 100:40 MCC MiS to MRL 1
151 100:40 EGSE Switch off N20 coupling 1
152 100:40 EGSE Switch off HE coupling 1
153 100:40 MRL Release Pneumatic lines Release Pneumatic lines of couplings 1 00:20
154 100:20 EGSE Confirm Fueling arm is off Confirm Fueling arm is switched off 1
155 100:20 EGSE Check OxOutPT and HPLPT 0 bar 1
156 100:20 MRL Couple Helium coupling 1 00:30
157 99:50 MRL Couple N2O coupling 1 00:30
158 99:20 MRL HOLD / RESTART 1
159 99:20 MRL BEGIN Arming Rocket SEQUENCE Part 1 BEGIN Arming Rocket Part 1 Arming 1 Arming Pt.1 1
160 99:20 MRL Connect Ignition Umbilical 1 00:30
161 98:50 MRL Turn on GoPro Camera at end of Launch Rail 1 00:20
162 98:30 MRL Insert EPS Bridges 1 03:00
165 95:10 OPS Elevate MRL to 90 degrees 1 05:00
166 90:10 EGSE Powercycle EPS to to start flight mode on Telemega 1 00:30
167 89:40 EGSE Calibrate loadcell (Set to 0) 1 01:00
168 88:40 MCC BEGIN Pressure Test Flight Segment (PHASE YELLOW) BEGIN Fuling Preparations (PHASE YELLOW) Pressure Test Rocket Fuling Preparations 2
169 88:40 MRL Put on safety equipment 2 00:30
170 88:10 MRL Open HE Bottle 1 Open He Bottle 1 2 01:00
171 87:10 MRL Step back 2
172 87:10 EGSE Open & Close stepwise MPV1/MPV2 to 50 Bar @ OxInPT1 & OxInPT2 Open & Close STEPWISE MPV1/MPV2 to 50 Bar @ OxInPT1 & OxInPT2 2
173 87:10 MRL Check & compare OxInPT1 with OxInPG1 based on Bottle temperature (max 50 bar) 2
174 87:10 MRL Check & compare pressure OxInPT2 with OxInPG2 based on Bottle temperature (max 50 bar) 2
175 87:10 MRL Check Temperature of N2O Bottle 1 @OxT1 & OxWT1 (max 22C) 2
194 125:50 OBDH Test Connection to STX3 1 00:20
195 125:30 OBDH Confirm that STX3 Package received by email 1 00:30
196 68:40 OBDH Acknowledge start of Fueling 3 01:00 CHANGE to 3 steps
197 67:40 EGSE Open & Close HPV1 to 50 Bar @ ROxTPT (stop at 30 bar and wait 30 seconds to check for leakage) Open & Close HPV1 STEPWISE to 50 Bar @ ROxTPT (stop at 30 bar and wait 30 seconds to check for leakage) 3
198 67:40 EGSE Open & Close HPV1 to more than 50 Bar @ RHPPT and check ROxTPT 50 Bar Open & Close HPV1 STEPWISE to more than 50 Bar @ RHPPT and check ROxTPT 50 Bar 3
199 67:40 EGSE Check if HPV1 is closed 3
200 67:40 OBDH Open RDV shortly, to check tightness @ RHPPT & ROxTPT (If leakages occur Abort) Open RDV SHORTLY, to check tightness @ RHPPT & ROxTPT (If leakages occur Abort) 3
201 67:40 EGSE Open MPV1/MPV2 3
202 67:40 EGSE Open & Close stepwise MPV3 to 50 Bar @ OxOutPT Open & Close MPV3 STEPWISE to 50 Bar @ OxOutPT 3
203 67:40 EGSE Close MPV1/MPV2 3
204 67:40 EGSE Check & compare OxOutPT with OxInPT1 3
205 67:40 EGSE Check if RHPPT & ROxTPT more than OxInPT1, If less Open & Close HPV1 3
206 67:40 EGSE Zero OxTank Mass 3
207 67:40 MCC Write down Time 3
208 67:40 EGSE Open OxV1 3 04:00
209 63:40 OBDH Open stepwise RDV until N2O bottle empty or 25kg OxTankMass, keep temperatures RDVT and RDVET above 10C and Check delta ROxTPT and OxInPT1 Open & Close RDV STEPWISE until N2O bottle empty or 25kg OxTankMass, keep temperatures RDVT and RDVET above 10C and Check delta ROxTPT and OxInPT1 3 30:00:00
210 33:40 EGSE Close OxV1 3 00:10
211 33:30 EGSE Check if Pressure rises in OxPT1, if Pressure rises relief via OxV1 or wait for Pressure relief valve 3 01:00
212 32:30 EGSE Check & compare OxOutPT with OxInPT2 3
213 32:30 EGSE Check & compare RHPPT & ROxTPT 50 Bar and more than OxInPT2, If less Open & Close HPV1 3
214 32:30 EGSE Open OxV2 3
215 32:30 OBDH Open stepwise RDV to 25kg OxTankMass, keep temperatures RDVT and RDVET above 10C and Check delta OxTPT and OxInPT1 Open & Close RDV STEPWISE to 25kg OxTankMass, keep temperatures RDVT and RDVET above 10C and Check delta OxTPT and OxInPT1 3 20:00
216 12:30 EGSE Close OxV2 3 00:10
217 12:20 EGSE Check if Pressure rises in OxPT2, if Pressure rises relief via OxV2 or wait for Pressure relief valve 3 01:00
218 11:20 EGSE Open stepwise OxDV until OxOutPT 0 Bar Open OxDV STEPWISE until OxOutPT 0 Bar 3
219 11:20 OBDH Check ROxCV for tightness @ ROxTPT 3
220 11:20 EGSE Close OxDV 3 01:00
221 10:20 EGSE Write down OxTankMass 3
245 6:30 PYL Confirm Payload is running 3 00:20
246 6:10 AVC Check if videorecording @ MCC is running 3 00:05
247 6:05 MCC High Pressure Fuling HP Fueling 3
248 6:05 EGSE Open and close HPV1 stepwise until RHPPT 300 Bar or pressure equal to HE Bottle 1 Open & Close HPV1 STEPWISE until RHPPT 300 Bar or pressure equal to HE Bottle 1 3
249 6:05 EGSE Open and close HPV2 stepwise until RHPPT 300 Bar Open & Close HPV2 STEPWISE until RHPPT 300 Bar 3
250 6:05 EGSE Open and close HPDV stepwise until HPLPT 0 Bar Open & close HPDV STEPWISE until HPLPT 0 Bar 3
251 6:05 EGSE Check HPDV closed 3
252 6:05 OBDH/EGSE Check for leakage HPLPT 0 Bar & RHPPT 300 Bar 3 02:00
253 4:05 OBDH Acknowledge end of Fueling 3 00:10
279 0:00 OBDH T+600: Verify (Landed) 4
280 0:00 MCC START OF PASSIVATION (PHASE YELLOW) (Write down Time) Passivation 2
281 0:00 MCC Turn audio volume up 2
282 0:00 TMTC Check ROxTPT & RHPPT 1 Bar, if more: Open & Close stepwise RDV Check ROxTPT & RHPPT 1 Bar, if more: Open & Close STEPWISE RDV 2
283 0:00 MRL Go to Testrig, Close N2O Bottle 1 & N2O Bottle 2 then RETURN to Block House 2
284 0:00 EGSE Open OxDV 2
285 0:00 EGSE Open OxV1 2