vers.;v4.5;Launch Procedure;;0;MRL;MCC;RdHill;Time per step; 147:20;MCC;BEGIN SEQUENCE: Power on EGSE;Power on EGSE;1;;;;; 147:20;EGSE;Check CLD connection;;1;;;;; 147:20;EGSE;Switch ON CLD via Battery & check voltage (24 Volt);;1;;;;; 147:20;EGSE;Switch ON the primary and secondary supply switches on the Control Panel;;1;;;;01:00; 146:20;EGSE@MRL;Switch ON Sup_24V_20A & check voltage (ca. 27,2 Volt);;1;;;;; 146:20;EGSE@MRL;Switch ON Sup_24V_10A & check voltage (ca. 27,2 Volt);;1;;;;; 146:20;EGSE@MRL;Switch ON Sup_12V_10A & check voltage (ca. 13,8 Volt);;1;;;;; 146:20;EGSE@MRL;Switch ON Bat_24V_20A & check voltage (ca. 27,9 Volt);;1;;;;; 146:20;EGSE@MRL;Switch ON Bat_24V_10A & check voltage (ca. 27,9 Volt);;1;;;;; 146:20;EGSE@MRL;Switch ON Bat_12V_10A & check voltage (ca. 13,8 Volt);;1;;;;; 146:20;EGSE@MRL;Switch ON Sup_24V_40A;;1;;;;; 146:20;EGSE@MRL;Switch ON Sup_5V_10A;;1;;;;03:00; 143:20;EGSE;Connect to cRIO;;1;;;;; 143:20;EGSE;Start FPGA_VI;;1;;;;; 143:20;EGSE;Start RT_VI;;1;;;;; 143:20;EGSE;Confirm PID-VI is running;;1;;;;; 143:20;EGSE;Rename PID-Logfile;;1;;;;02:00; 141:20;MRL;Confirm working Personel is grounded;;1;;;;; 141:20;EGSL@MRL;Confirm all 8 Groundingbridges are inserted;;1;;;;; 141:20;MCC;BEGIN SEQUENCE: Connect Data Umbilical;Connect Data Umbilical;1;;;;00:30; 140:50;EGSE;Turn on EPS_BAT;;1;;;;; 140:50;EGSE;Turn on EPS_EXT;;1;;;;; 140:50;EGSE@MRL;Remove 7 Grounding Bridges and leave EPS_BAT inserted;;1;;;;; 140:50;EGSE@MRL;Insert EPS_EXT Fuse in Power Supply Control Panel;;1;;;;; 140:50;EGSE@MRL;Confirm green LED at EPS_EXT Fuse is on;;1;;;;; 140:50;EGSE@MRL;Insert Main_Bus Fuse in Power Supply Control Panel;;1;;;;; 140:50;EGSE@MRL;Confirm LED at Main_Bus Fuse is OFF. Else Pull fuse and insert all Grounding Bridges;;1;;;;; 140:50;EGSE@MRL;Set remaining Fuses (except Payload Fuse) and check for green LED;;1;;;;; 140:50;EGSE;Turn OFF EPS_BAT;;1;;;;; 140:50;EGSE@MRL;Confirm Main bus LED is on.;;1;;;;; 140:50;EGSE;Start EPS via EPS_ext;;1;;;;; 140:50;OBDH;Clear SD-Card-using FileZilla FTP;;1;;;;01:00; 139:50;OBDH;Connect to sbRIO;;1;;;;; 139:50;OBDH;Start RT_Main;;1;;;;; 139:50;MRL;Confirm 3 beeps at OBC1;;1;;;;; 139:50;OBDH;Open RT_Sub_HMI;;1;;;;; 139:50;OBDH;Confirm Main Chute button is disabled;;1;;;;; 139:50;EGSE@MRL;Insert Payload Fuse;;1;;;;; 139:50;EGSE@MRL;Confirm green LED at Payload Fuse is on;;1;;;;; 139:50;MCC;BEGIN SEQUENCE: Connect Fueling arm;Connect Fueling Arm;1;;;;; 139:50;MRL;Confirm working Personel is grounded;;1;;;;01:00; 138:50;MRL;Remove Pneumatic Line from Fueling arm;;1;;;;; 138:50;MRL;Move Fueling arm to rocket;;1;;;;; 138:50;MRL;Couple Helium coupling;;1;;;;; 138:50;MRL;Couple N2O coupling;;1;;;;; 138:50;MRL;Reattach Pneumatic Line to Fueling arm;;1;;;;03:00; 135:50;EGSE;BEGIN SEQUENCE: EGSE Valve and Actuator check;EGSE Valve & Actuator Check;1;;;;; 135:50;MCC;Confirm that video recording is enabled @ MCC;;1;;;;00:10; 135:50;MRL;Confirm that Ignition Umbilical is disconnected;;1;;;;; 135:40;OBDH;Check EPS hardware Voltages;;1;;;;00:10; 135:30;EGSE;Start PID data recording;;1;;;;00:10; 135:20;MRL;Close HPNV;;1;;;;00:10; 135:10;EGSE/MRL;Switch OxDV to closed & check if magnetic valve LED is on;;1;;;;00:10; 135:00;EGSE/MRL;Switch HPDV to closed & check if magnetic valve LED is on;;1;;;;00:10; 134:50;EGSE/MRL;Check warning lamp on HPSM;;1;;;;00:10; 134:40;MRL;Remove loose equipment;;1;;;;03:00; 131:40;EGSE;Activate Heizi;;1;;;;00:10; 131:30;EGSE;Activate N2O_Heater 1;;1;;;;00:10; 131:20;EGSE;Activate N2O_Heater 2;;1;;;;00:10; 131:10;EGSE;Activate He_Heater;;1;;;;00:10; 131:00;OBDH;Verify Heizi @ RDVT & RDVET;;1;;;;00:10; 130:50;EGSE/MRL;Verify Bottle Temperatures @ OxT1, OxT2, HPT2;;1;;;;00:10; 130:40;EGSE/MRL;Verify Water Temperatures @ Ox@T1, OxWT2, HPWT2;;1;;;;00:10; 130:30;EGSE;Deactivate Heizi;;1;;;;00:10; 130:20;EGSE;Check OxV1 (CLD & RT_VI);;1;;;;00:10; 130:10;EGSE;Check OxV2 (CLD & RT_VI);;1;;;;00:10; 130:00;EGSE;Check MPV3 (CLD & RT_VI);;1;;;;00:10; 129:50;EGSE;Check HPV1 (CLD & RT_VI);;1;;;;00:10; 129:40;EGSE;Check HPV2 (CLD & RT_VI);;1;;;;00:10; 129:30;EGSE;Check MPV1/2 (CLD & RT_VI);;1;;;;00:10; 129:20;EGSE;Check RDV (CLD & RT_VI);;1;;;;00:10; 129:10;EGSE;Check RMOxOV (CLD & RT_VI);;1;;;;00:10; 129:00;EGSE;Check RMOxSV (CLD & RT_VI);;1;;;;00:10; 128:50;OBDH;Activate Heizi;;1;;;;00:10; 128:40;OBDH;Verify Heizi @ RDVT & RDVET;;1;;;;01:00; 127:40;OBDH;Check RDV;;1;;;;00:10; 127:30;OBDH;Check RNCEV;;1;;;;00:10; 127:20;OBDH;Check RMOxOV;;1;;;;00:10; 127:10;OBDH;Check RMOxSV;;1;;;;00:10; 127:00;OBDH;Confirm RNCEV is disabled;;1;;;;00:10; 125:00;MRL;Confirm MBV closed;;1;;;;; 125:00;EGSE;Confirm that all valve switches are in OFF position (Except OxDV & HPDV);;1;;;;0:10; 115:00;MRL/EGSE;Check loadcell by applying force to it;;1;;;;00:20; 114:40;OBDH;Check RHPPT shows atmosphere;;1;;;;; 114:40;OBDH;Check ROxTPT shows atmosphere;;1;;;;; 114:40;OBDH;Check RIHPT shows atmosphere;;1;;;;; 114:40;OBDH;Check RCCPT shows atmosphere;;1;;;;; 114:40;OBDH;Check RBaro1 shows atmosphere;;1;;;;; 114:40;OBDH;Check RBaro2 shows atmosphere;;1;;;;; 114:40;EGSE;Check HPPT1 shows 0 bar;;1;;;;00:20; 114:20;EGSE;Check HPPT2 shows 0 bar;;1;;;;; 114:20;EGSE;Check HPLPT shows 0 bar;;1;;;;; 114:20;EGSE;Check OxInPT1 shows 0 bar;;1;;;;; 114:20;EGSE;Check OxInPT2 shows 0 bar;;1;;;;; 114:20;EGSE;Check OxOutPT shows 0 bar;;1;;;;00:20; 114:00;EGSE/MRL;Switch on N2O coupling & check if magnetic valve LED is on;;1;;;;; 114:00;EGSE/MRL;Switch on He coupling & check if magnetic valve LED is on;;1;;;;; 114:00;EGSE/MRL;Switch on swivle arm & check if magnetic valve LED is on;;1;;;;; 114:00;EGSE;Switch off swivel arm & He coupling & N2O coupling;;1;;;;01:00; 114:00;MCC;BEGIN SEQUENCE: Ignition signal Test;Ignition signal Test;1;;;;01:00; 113:00;MRL;Confirm that Ignition Umbilical is disconnected;;1;;;;; 113:00;MRL;Connect Ignition test receptical;;1;;;;; 113:00;EGSE@MRL;Plug in Bridges B1 and B2;;1;;;;; 113:00;MRL;Confirm Soundsignal from Ignition Umbilical;;1;;;;; 113:00;EGSE;Turn on Ignition Secure Switch;;1;;;;; 113:00;EGSE/OBDH;Turn on Ignition Switch for 2 Second & Confirm ignition signal received at sbRio;;1;;;;; 113:00;EGSE/OBDH;Confirm that Ignition Switch is switched off;;1;;;;; 113:00;EGSE;Turn off Ignition Secure Switch;;1;;;;; 113:00;EGSE@MRL;Remove Bridges B1 and B2;;1;;;;; 113:00;MRL;Remove Ignition test receptical;;1;;;;03:00; 110:00;MCC;BEGIN SEQUENCE: pneumatic pressure test (PHASE YELLOW) ;Pneumatic Pressure Test;1;;;;; 110:00;EGSE/MRL;Verify Bottle Temperatures @ OxT1, OxT2, HPT2;;1;;;;00:10; 110:00;EGSE/MRL;Verify Water Temperatures @ Ox@T1, OxWT2, HPWT2;;1;;;;00:10; 110:00;MRL;Confirm that all hatches are closed;;1;;;;01:00; 109:00;MRL;Check He bottle 1 connector is attached;;1;;;;; 109:00;MRL;Check He bottle 2 connector is attached;;1;;;;; 109:00;MRL;Check N2O bottle 1 connector is attached;;1;;;;; 109:00;MRL;Check N2O bottle 2 connector is attached;;1;;;;; 109:00;MRL;Check hose between HPSM & N2OSM is connected on both ends;;1;;;;; 109:00;MRL;Check hose between HPSM & Flight Segment is connected on both ends;;1;;;;; 109:00;MRL;Check hose between N2OSM & Flight Segment is connected on both ends;;1;;;;; 109:00;MRL;Check Pneumatik hose is connected on both ends;;1;;;;02:00; 107:00;MRL;Put on safety equipment;;2;;;;; 107:00;MRL;Move into Position to open He Bottle 1;;2;;;;; 107:00;MRL;Confirm MBV is closed;;2;;;;; 107:00;EGSE;Confirm if HPV1 is closed;;2;;;;; 107:00;EGSE;Confirm MPV1/2 is closed;;2;;;;; 107:00;MRL;Open He Bottle 1;;2;;;;01:00; 106:00;MRL;Check & compare pressure HPPT1 with HPPG1 (max 300 bar);;2;;;;; 106:00;MRL;Check Gastech Silver HPPR1 (max 300 to 50 bar);;2;;;;; 106:00;MRL;Check Harris PPR (50 to 8 bar);;2;;;;; 106:00;MRL;Check pneumatic PPG (8 bar);;2;;;;; 106:00;MRL;Step back;;2;;;;01:00; 105:00;EGSE/MRL;Open & Close HPV1 SHORTLY & Check HPPT1;;2;;;;; 105:00;EGSE;Confirm HPPT1 is at 300 Bar;;2;;;;; 105:00;EGSE;Confirm HPLPT less than 10 Bar;;2;;;;; 105:00;EGSE/MRL;Open & Close HPV2 SHORTLY & Check HPPT2 0 bar;;2;;;;; 105:00;EGSE/MRL;Open & Close HPDV SHORTLY & Check HPLPT 0 bar;;2;;;;; 105:00;EGSE/MRL;Open & Close OxV1 SHORTLY;;2;;;;; 105:00;EGSE/MRL;Open & Close OxV2 SHORTLY;;2;;;;; 105:00;EGSE/MRL;Open & Close OxDV SHORTLY;;2;;;;; 105:00;EGSE/MRL;Open & Close MPV3 SHORTLY;;2;;;;; 105:00;EGSE;Check HPLPT & OxOutPT 0 Bar;;2;;;;01:30; 103:30;EGSE;Decouple N2O coupling;;2;;;;; 103:30;EGSE;Decouple Helium coupling;;2;;;;00:20; 103:10;EGSE;Move arm away from rocket;;2;;;;; 103:10;EGSE;Move arm to rocket;;2;;;;01:00; 102:10;MRL;Close He Bottle 1 and check HPSM for leakage (If leakage occurs Abort);;2;;;;01:00; 101:10;MRL;Open HPNV 1/8 Rev;;2;;;;; 101:10;MRL;Open MBV;;2;;;;; 101:10;EGSE/MRL;Check and compare pressure HPPT1 with HPPG1 0 Bar;;2;;;;; 101:10;MRL;Close MBV;;2;;;;00:30; 100:40;MRL;Safety is ensured;;2;;;;; 100:40;MCC;MiS to MRL;;1;;;;; 100:40;EGSE;Switch off N20 coupling;;1;;;;; 100:40;EGSE;Switch off He coupling;;1;;;;; 100:40;MRL;Release Pneumatic lines of couplings;;1;;;;00:20; 100:20;EGSE;Confirm Fueling arm is switched off;;1;;;;; 100:20;EGSE;Check OxOutPT and HPLPT 0 bar;;1;;;;; 100:20;MRL;Couple Helium coupling;;1;;;;00:30; 99:50;MRL;Couple N2O coupling;;1;;;;00:30; 99:20;MRL;HOLD;HOLD;1;;;;; 99:20;EGSE/MRL;Verify Bottle Temperatures @ OxT1, OxT2, HPT2;;1;;;;00:10; 99:20;EGSE/MRL;Verify Water Temperatures @ Ox@T1, OxWT2, HPWT2;;1;;;;00:10; 99:20;MCC;CONTINUE AFTER HOLD;;;;;;; 99:20;MRL;BEGIN SEQUENCE: Arming Rocket Part 1;Arming Rocket Pt.1;1;;;;; 98:50;MRL;Turn on GoPro Camera at end of Launch Rail;;1;;;;00:20; 99:20;MRL;Connect Ignition Umbilical;;1;;;;00:30; 98:30;MRL;Insert all EPS Bridges;;1;;;;03:00; 95:30;MRL;Confirm Bridge Hatch is Secured;;1;;;;00:20; 95:10;EGSE@MRL;return to MCC;;1;;;;; 95:10;OPS;Elevate MRL to 90 degrees;;1;;;;05:00; 90:10;EGSE;Powercycle EPS to to start flight mode on Telemega;;1;;;;00:30; 89:40;EGSE;Calibrate loadcell (Set to 0);;1;;;;01:00; 88:40;MCC;BEGIN SEQUENCE: Fueling Preparations (PHASE YELLOW);Fueling Preparations;2;;;;; 89:40;EGSE/MRL;Verify Bottle Temperatures @ OxT1, OxT2, HPT2;;1;;;;00:10; 89:40;EGSE/MRL;Verify Water Temperatures @ Ox@T1, OxWT2, HPWT2;;1;;;;00:10; 88:40;MRL;Put on safety equipment;;2;;;;00:30; 88:10;MRL;Open He Bottle 1;;2;;;;01:00; 87:10;MRL;Step back;;2;;;;; 87:10;EGSE;Open & Close STEPWISE MPV1/MPV2 to 50 Bar @ OxInPT1 & OxInPT2;;2;;;;; 87:10;EGSE/MRL;Check & compare OxInPT1 with OxInPG1 based on Bottle temperature (max 50 bar);;2;;;;; 87:10;EGSE/MRL;Check & compare pressure OxInPT2 with OxInPG2 based on Bottle temperature (max 50 bar);;2;;;;; 87:10;EGSE/MRL;Check Temperature of N2O Bottle 1 @OxT1 & OxWT1 (max 22C);;2;;;;; 87:10;EGSE/MRL;Check Temperature of N2O Bottle 2 @OxT2 & OxWT2 (max 22C);;2;;;;01:30; 85:40;MRL;Open He Bottle 2;;2;;;;; 85:40;EGSE/MRL;Check & compare pressure HPPT2 with HPPG2 (max 315 bar);;2;;;;01:00; 84:40;ALL/MRL;CAUTION!;;2;;;;; 84:40;MRL;Open N2O Bottle 1;;2;;;;; 84:40;MRL/EGSE;Check & compare pressure OxInPT 1 with OxInPG 1 (max 50 bar);;2;;;;02:00; 82:40;MRL;Open N2O Bottle 2;;2;;;;; 82:40;MRL/EGSE;Check & compare pressure OxInPT 2 with OxInPG 2 (max 50 bar);;2;;;;02:00; 80:40;MRL;Insert Ignition Bridges B1 and B2 into EGSE;;2;;;;02:00; 78:40;MRL;Confirm Soundsignal from Ignition Umbilical;;2;;;;; 78:40;MRL;Close ComTerm;;2;;;;; 78:40;MCC;Turn Off MRL lock;;2;;;;; 78:40;ALL;Clear Launchpad and inform OPS;;2;;;;10:00; 68:40;KLP;Start Camera Karsten Lappöhn;;2;;;;; 68:40;MCC;HOLD;HOLD;2;;;;; 68:40;EGSE;Verify Bottle Temperatures @ OxT1, OxT2, HPT2;;1;;;;00:10; 68:40;EGSE;Verify Water Temperatures @ Ox@T1, OxWT2, HPWT2;;1;;;;00:10; 68:40;MCC;CONTINUE AFTER HOLD;;;;;;; 68:40;MCC;BEGIN SEQUENCE Ox Fueling (PHASE RED);Ox Fueling (PHASE RED);3;;;;; 68:40;MCC;Announce end of Radio Silence;;3;;;;; 68:40;OBDH/TMTC;Check RF451-Link;;1;;;;00:20; 68:40;TMTC;Confirm GPS-lock;;1;;;;00:20; 68:40;TMTC;Confirm Telemega-Link;;1;;;;00:20; 68:40;OBDH;Test Connection to STX3;;1;;;;00:20; 68:40;OBDH;Confirm that STX3 Package received by email;;1;;;;00:30; 68:40;MCC;Request Permission to begin fueling from OPS;;1;;;;03:00; 68:40;OBDH;Acknowledge start of Fueling;;3;;;;01:00; 67:40;EGSE;Open & Close HPV1 STEPWISE to 50 Bar @ ROxTPT (stop at 30 bar and wait 30 seconds to check for leakage);;3;;;;; 67:40;EGSE;Open & Close HPV1 STEPWISE to more than 50 Bar @ RHPPT and check ROxTPT 50 Bar;;3;;;;; 67:40;EGSE;Check if HPV1 is closed;;3;;;;; 67:40;OBDH;Open RDV SHORTLY, to check tightness @ RHPPT & ROxTPT (If leakages occur Abort);;3;;;;; 67:40;EGSE;Open MPV1/MPV2;;3;;;;; 67:40;EGSE;Open & Close MPV3 STEPWISE to 50 Bar @ OxOutPT;;3;;;;; 67:40;EGSE;Close MPV1/MPV2;;3;;;;; 67:40;EGSE;Check & compare OxOutPT with OxInPT1;;3;;;;; 67:40;EGSE;Check if RHPPT & ROxTPT more than OxInPT1, If less Open & Close HPV1;;3;;;;; 67:40;EGSE;Zero OxTank Mass;;3;;;;; 67:40;MCC;Write down Time;;3;;;;; 67:40;EGSE;Open OxV1;;3;;;;04:00; 63:40;OBDH;Open & Close RDV STEPWISE until N2O bottle empty or 25kg OxTankMass, keep temperatures RDVT and RDVET above 10°C and Check delta ROxTPT and OxInPT1;;3;;;;30:00:00; 33:40;EGSE;Verify Bottle Temperatures @ OxT1, OxT2, HPT2;;1;;;;00:10; 33:40;EGSE;Verify Water Temperatures @ Ox@T1, OxWT2, HPWT2;;1;;;;00:10; 33:40;EGSE;Close OxV1;;3;;;;00:10; 33:30;EGSE;Check if Pressure rises in OxPT1, if Pressure rises relief via OxV1 or wait for Pressure relief valve;;3;;;;01:00; 32:30;EGSE;Check & compare OxOutPT with OxInPT2;;3;;;;; 32:30;EGSE;Check & compare RHPPT & ROxTPT 50 Bar and more than OxInPT2, If less Open & Close HPV1;;3;;;;; 32:30;EGSE;Open OxV2 ;;3;;;;; 32:30;OBDH;Open & Close RDV STEPWISE to 25kg OxTankMass, keep temperatures RDVT and RDVET above 10°C and Check delta OxTPT and OxInPT1;;3;;;;20:00; 12:30;EGSE;Close OxV2 ;;3;;;;00:10; 12:20;EGSE;Check if Pressure rises in OxPT2, if Pressure rises relief via OxV2 or wait for Pressure relief valve;;3;;;;01:00; 11:20;EGSE;Open OxDV STEPWISE until OxOutPT 0 Bar;;3;;;;; 11:20;OBDH;Check ROxCV for tightness @ ROxTPT;;3;;;;; 11:20;EGSE;Close OxDV;;3;;;;01:00; 10:20;EGSE;Write down OxTankMass;;3;;;;; 10:20;MCC;Provide OxTankMass and temperature readings to Wind weighting station;;3;;;;00:30; 9:50;EGSE;Confirm OxV1 & OxV2 closed;;3;;;;; 9:50;EGSE;Check OxOutPT 0 Bar;;3;;;;; 9:50;EGSE;Decouple N2O coupling;;3;;;;00:20; 9:30;MCC;Confirm End of Oxidator Fueling to OPS;;3;;;;00:15; 9:15;OBDH/TMTC;Check RF451-Link;;3;;;;00:20; 8:55;TMTC;Check GPS-lock;;3;;;;00:20; 8:35;TMTC;Check Telemega-Link;;3;;;;00:20; 8:15;MCC;HOLD;HOLD;3;;;;; 8:15;OPS;Align MRL to Launch Trajectory;;3;;;;; 8:15;MCC;Turn audio volume down;;3;;;;; 8:15;MCC;Turn off Confirm delay;;3;;;;; 8:15;MCC;Confirm MRL adjustment with OPS;;3;;;;; 8:15;ALL;Talk through Launch Sequence;;3;;;;; 8:15;AVC;Start Video Recording in Block House;;3;;;;; 8:15;MCC;CONTINUE AFTER HOLD;;;;;;; 8:15;MCC;BEGIN Switching to Internal Power Sequence;Switch to Internal Power;3;;;;; 8:15;EGSE;Switch to internal Power;;3;;;;00:20; 7:55;OBDH;Confirm EPS Voltages are within limits;;3;;;;00:10; 7:45;OBDH;Confirm RF451 Transmitting;;3;;;;00:05; 7:40;OBDH/TMTC;Confirm RF451-Link;;3;;;;00:20; 7:20;TMTC;Confirm GPS-lock;;3;;;;00:20; 7:00;TMTC;Confirm Telemega-Link;;3;;;;00:20; 6:40;OBDH;Switch to PREAMRED;;3;;;;00:10; 6:30;PYL;Confirm Payload is running;;3;;;;00:20; 6:10;AVC;Confirm that videorecording @ MCC is running;;3;;;;00:05; 6:05;MCC;BEGIN SEQUENCE: High Pressure Fueling;High Pressure Fueling;3;;;;; 6:05;EGSE;Open & Close HPV1 STEPWISE until RHPPT 300 Bar or pressure equal to He Bottle 1;;3;;;;; 6:05;EGSE;Open & Close HPV2 STEPWISE until RHPPT 300 Bar ;;3;;;;; 6:05;EGSE;Open & close HPDV STEPWISE until HPLPT 0 Bar ;;3;;;;; 6:05;EGSE;Confirm HPDV closed;;3;;;;; 6:05;OBDH/EGSE;Check for leakage & HPLPT 0 Bar & RHPPT 300 Bar ;;3;;;;02:00; 4:05;OBDH;Acknowledge end of Fueling;;3;;;;00:10; 3:55;MCC;Confirm End of Fueling to OPS;;3;;;;00:20; 3:35;MCC;BEGIN SEQUENCE: Disconnecting Fueling Arm;Disconnecting Fueling Arm;3;;;;00:10; 3:25;EGSE;Confirm HPV1 & HPV2 closed;;3;;;;00:10; 3:15;EGSE;Check HPLPT 0 Bar ;;3;;;;00:10; 3:05;EGSE;Decouple Helium coupling;;3;;;;00:20; 2:45;EGSE;Confirm Helium coupling is disconnected;;3;;;;00:10; 2:35;EGSE;Move fueling arm away from rocket;;3;;;;00:40; 1:55;MCC;Confirm Fueling Arm away to OPS;;3;;;;00:15; 1:40;MCC;Prepare for Launch;;3;;;;00:10; 1:30;OBDH;Confirm ready for launch;;3;;;;00:10; 1:20;EGSE;Confirm ready for launch;;3;;;;00:10; 1:10;MCC;Set Go/No-Go System to Go;;3;;;;00:10; 1:00;MCC;Wait for Authorization for Launch;;3;;;;00:00; 1:00;MCC;BEGIN SEQUENCE: Ignition;Ignition Sequence;4;;;;00:10; 0:50;OBDH;ARM;;4;;;;00:05; 0:45;OBDH;Confirm all status indicators green;;4;;;;00:05; 0:40;OBDH;Disconnect Ethernet;;4;;;;00:30; 0:10;EGSE;Turn on Ignition Secure;;4;;;;00:07; 0:03;EGSE;T-3: Ignition;;4;;;;00:03; 0:00;OBDH;T+0: Verify RMOxOV Open (Launched);;4;;;;00:00; 0:00;EGSE;T+1: Turn OFF Ignition;;4;;;;; 0:00;EGSE;T+5: Turn OFF Ignition Secure;;4;;;;; 0:00;OBDH;T+20: Verify RMOxOV Closed and RMOxSV Open (Cruise);;4;;;;; 0:00;OBDH;T+50: Verify RNCEV Open (Drogue);;4;;;;; 0:00;OBDH;T+310: Verify Main Chute Deployed and RDV Open (Main);;4;;;;; 0:00;OBDH;T+600: Verify (Landed);;4;;;;; 0:00;MCC;BEGIN SEQUENCE: PASSIVATION (PHASE YELLOW) (Write down Time);Passivation;2;;;;; 0:00;MCC;Turn audio volume up;;2;;;;; 0:00;TMTC;Check ROxTPT & RHPPT 1 Bar, if more: Open & Close STEPWISE RDV;;2;;;;; 0:00;MRL;Go to Testrig, Close N2O Bottle 1 & N2O Bottle 2 then RETURN to Block House;;2;;;;; 0:00;EGSE;Open OxDV;;2;;;;; 0:00;EGSE;Open OxV1;;2;;;;; 0:00;EGSE;Check OxInPT1 & OxOutPT 0 Bar;;2;;;;; 0:00;EGSE;Close OxV1;;2;;;;; 0:00;EGSE;Open OxV2;;2;;;;; 0:00;EGSE;Check OxInPT2 & OxOutPT 0 Bar;;2;;;;; 0:00;EGSE;Close OxV2;;2;;;;; 0:00;EGSE;Close OxDV ;;2;;;;; 0:00;MRL;Go to MRL, confirm OxInPG1 & OxInPG2 0 Bar, else RETURN to Block House, THEN... 0:00;MRL;Close He Bottle 2, THEN...;;2;;;;; 0:00;MRL;Write down remaining Pressure of He Bottle 2, THEN...;;2;;;;; 0:00;MRL;Return to Block House;;2;;;;; 0:00;EGSE;Open HPDV;;2;;;;; 0:00;EGSE;Open HPV2;;2;;;;; 0:00;EGSE;Check pressure HPLPT & HPPT2 0 Bar;;2;;;;; 0:00;EGSE;Close HPV2;;2;;;;; 0:00;EGSE;Close HPDV;;2;;;;; 0:00;MRL;Go to Testrig, confirm HPPG2 0 Bar, else return to Block House, THEN...;;2;;;;; 0:00;MRL;Close He Bottle 1, THEN ...;;2;;;;; 0:00;MRL;Open ComTerm;;2;;;;; 0:00;MCC;Turn on MRL lock;;2;;;;; 0:00;MRL;Write down remaining Pressure of He Bottle 1;;2;;;;; 0:00;MRL;Step back;;2;;;;; 0:00;EGSE;Open HPDV;;2;;;;; 0:00;EGSE;Open HPV1;;2;;;;; 0:00;EGSE;Check pressure HPLPT & HPPT1 0 Bar;;2;;;;; 0:00;EGSE;Close HPV1;;2;;;;; 0:00;EGSE;Close HPDV;;2;;;;; 0:00;EGSE;Pressure Check;;2;;;;; 0:00;MRL;Open MBV;;2;;;;; 0:00;EGSE/MRL;Check and compare pressure HPPT1 with HPPG1;;2;;;;; 0:00;MRL;Close MBV;;2;;;;; 0:00;MRL;Take out B1 & B2 Bridges;;2;;;;; 0:00;MRL;Safety is ensured;;2;;;;; 0:00;MCC;Confirm to OPS that Safety is ensured;;1;;;;; 0:00;MCC;BEGIN SEQUENCE: Data collection;Data collection;1;;;;; 0:00;AVC;Turn off GoPro & Camcorder & Stop Block House Video recording;;1;;;;; 0:00;EGSE;Copy PID.vi.tdms & save to new name;;1;;;;; 0:00;EGSE;Wait for buffer storage process to be finished;;1;;;;; 0:00;EGSE;save data files from cRIO to PC;;1;;;;; 0:00;AVC;End audio recording;;1;;;;; 0:00;MCC;Stop ComTerm and save logfile to external HDD, THEN...;;1;;;;; 0:00;MCC;Restart ComTerm VI;;1;;;;; 0:00;AVC;Save video & audio data on external HDD;;1;;;;; 0:00;MCC;END OF PROCEDURE;;1;;;;;