Launch Procedure v3.0

This commit is contained in:
Finn 2020-02-20 17:42:25 +01:00
commit 6599484559
2 changed files with 358 additions and 0 deletions

48
AbortProcedure.csv Normal file
View File

@ -0,0 +1,48 @@
vers.;v2.4;Abort Procedure;;3
0;ALL;BEGIN ABORT PROCEDURE;;3
0;EGSE;Confirm all valve switches are in OFF position (Except OxDV & HPDV);;3
0;OBDH;Confirm all valve switches are in OFF position (Except RMOxSV);;3
0;EGSE;Open OxDV stepwise;;3
0;EGSE;Open MPV3;;3
0;EGSE;Check OxOutPT 0 bar;;3
0;EGSE;Close MPV3;;3
0;EGSE;Close OxDV;;3
0;EGSE;Check OxOutPT 0 bar;;3
0;EGSE;Open HPDV;;3
0;EGSE;Check HPLPT 0 bar;;3
0;EGSE;Close HPDV;;3
0;OBDH;Check ROxTPT & RHPPT 1 Bar, if more: Open & Close stepwise RDV;;3
0;OBDH;Deactivate Heizi;;2
0;MRL;Go to MRL;;2
0;MRL;Close N2O Bottle 1 & N2O Bottle 2;;2
0;MRL;Go to BlockHouse;;2
0;EGSE;Open OxDV;;2
0;EGSE;Open OxV1;;2
0;EGSE;Check OxInPT1 & OxOutPT 0 Bar;;2
0;EGSE;Close OxV1;;2
0;EGSE;Open OxV2;;2
0;EGSE;Check OxInPT2 & OxOutPT 0 Bar;;2
0;EGSE;Close OxV2;;2
0;EGSE;Close OxDV ;;2
0;MRL;Go to MRL;;2
0;MRL;Confirm OxInPG1 & OxInPG2 0 Bar;;2
0;MRL;Close HE Bottle;;2
0;MRL;Write down remaining Pressure of HE Bottle;;2
0;MRL;Go to BlockHouse;;2
0;EGSE;Open HPDV;;2
0;EGSE;Open HPV2;;2
0;EGSE;Check pressure HPLPT & HPPT2 0 Bar;;2
0;EGSE;Close HPV2;;2
0;EGSE;Close HPDV;;2
0;MRL;Go to MRL;;2
0;MRL;Confirm HPPG2 0 Bar;;2
0;MRL;Close N2 Bottle;;2
0;MRL;Write down remaining Pressure of N2 Bottle;;2
0;MRL;Step back;;2
0;MRL;Open MBV;;2
0;EGSE;Check and compare pressure HPPT1 with HPPG1;;2
0;MRL;Close MBV;;2
0;MRL;Disconnect Zündi;;2
0;MRL;Safety is ensured;;2
0;MCC;Turn off area warning light and open barrier;;1
0;MCC;END OF ABORT Procedure (PHASE GREEN) (Write down Time);;1
1 vers. v2.4 Abort Procedure 3
2 0 ALL BEGIN ABORT PROCEDURE 3
3 0 EGSE Confirm all valve switches are in OFF position (Except OxDV & HPDV) 3
4 0 OBDH Confirm all valve switches are in OFF position (Except RMOxSV) 3
5 0 EGSE Open OxDV stepwise 3
6 0 EGSE Open MPV3 3
7 0 EGSE Check OxOutPT 0 bar 3
8 0 EGSE Close MPV3 3
9 0 EGSE Close OxDV 3
10 0 EGSE Check OxOutPT 0 bar 3
11 0 EGSE Open HPDV 3
12 0 EGSE Check HPLPT 0 bar 3
13 0 EGSE Close HPDV 3
14 0 OBDH Check ROxTPT & RHPPT 1 Bar, if more: Open & Close stepwise RDV 3
15 0 OBDH Deactivate Heizi 2
16 0 MRL Go to MRL 2
17 0 MRL Close N2O Bottle 1 & N2O Bottle 2 2
18 0 MRL Go to BlockHouse 2
19 0 EGSE Open OxDV 2
20 0 EGSE Open OxV1 2
21 0 EGSE Check OxInPT1 & OxOutPT 0 Bar 2
22 0 EGSE Close OxV1 2
23 0 EGSE Open OxV2 2
24 0 EGSE Check OxInPT2 & OxOutPT 0 Bar 2
25 0 EGSE Close OxV2 2
26 0 EGSE Close OxDV 2
27 0 MRL Go to MRL 2
28 0 MRL Confirm OxInPG1 & OxInPG2 0 Bar 2
29 0 MRL Close HE Bottle 2
30 0 MRL Write down remaining Pressure of HE Bottle 2
31 0 MRL Go to BlockHouse 2
32 0 EGSE Open HPDV 2
33 0 EGSE Open HPV2 2
34 0 EGSE Check pressure HPLPT & HPPT2 0 Bar 2
35 0 EGSE Close HPV2 2
36 0 EGSE Close HPDV 2
37 0 MRL Go to MRL 2
38 0 MRL Confirm HPPG2 0 Bar 2
39 0 MRL Close N2 Bottle 2
40 0 MRL Write down remaining Pressure of N2 Bottle 2
41 0 MRL Step back 2
42 0 MRL Open MBV 2
43 0 EGSE Check and compare pressure HPPT1 with HPPG1 2
44 0 MRL Close MBV 2
45 0 MRL Disconnect Zündi 2
46 0 MRL Safety is ensured 2
47 0 MCC Turn off area warning light and open barrier 1
48 0 MCC END OF ABORT Procedure (PHASE GREEN) (Write down Time) 1

310
LaunchProcedure.csv Normal file
View File

@ -0,0 +1,310 @@
vers.;v3.0;Launch Procedure;;0;MRL;MCC;Radar Hill;Time per step;
148:35;EGSE;Check CLD connection;;1;;;;;
148:35;EGSE;Switch on CLD via Battery & check voltage (24 Volt);;1;;;;;
148:35;EGSE;Switch on the primary and secondary supply switches on the Control Panel;;1;;;;01:00;
147:35;EGSE;Power on EGSE;Power on EGSE;1;;;;;
147:35;EGSE@MRL;Switch on Sup_24V_20A & check voltage (ca. 27,2 Volt);;1;;;;;
147:35;EGSE@MRL;Switch on Sup_24V_10A & check voltage (ca. 27,2 Volt);;1;;;;;
147:35;EGSE@MRL;Switch on Sup_12V_10A & check voltage (ca. 13,8 Volt);;1;;;;;
147:35;EGSE@MRL;Switch on Bat_24V_20A & check voltage (ca. 27,9 Volt);;1;;;;;
147:35;EGSE@MRL;Switch on Bat_24V_10A & check voltage (ca. 27,9 Volt);;1;;;;;
147:35;EGSE@MRL;Switch on Bat_12V_10A & check voltage (ca. 13,8 Volt);;1;;;;;
147:35;EGSE@MRL;Switch on Sup_24V_40A;;1;;;;;
147:35;EGSE@MRL;Switch on Sup_5V_10A;;1;;;;03:00;
144:35;EGSE;Connect to cRIO;;1;;;;;
144:35;EGSE;Start FPGA_VI;;1;;;;;
144:35;EGSE;Start RT_VI;;1;;;;;
144:35;EGSE;Confirm PID-VI is running;;1;;;;;
144:35;EGSE;Rename PID-Logfile;;1;;;;02:00;
142:35;MRL;Confirm working Personel is grounded;;1;;;;;
142:35;MRL;Connect Data Umbilical;Connect Data Umbilical;1;;;;00:30;
142:05;EGSE;Start EPS via EPS_ext;;1;;;;;
142:05;EGSE@MRL;Set Fuse in Power supply control panel;;1;;;;;
142:05;EGSE@MRL;Insert EPS_bat Bridge;;1;;;;02:00;
140:05;OBDH;Clear SD-Card-using FileZilla FTP;;;;;;01:00;
139:05;OBDH;Connect to sbRIO;;1;;;;;
139:05;OBDH;Start RT_Main;;1;;;;;
139:05;MRL;Confirm 3 beeps at OBC1;;1;;;;;
139:05;OBDH;Open RT_Sub_HMI;;1;;;;;
139:05;OBDH;Confirm Main Chute button is disabled;;1;;;;;
139:05;MRL;Confirm working Personel is grounded;;1;;;;01:00;
138:05;MRL;Remove Pneumatic Line from Fueling arm;;1;;;;;
138:05;MRL;Move Fueling arm to rocket;;1;;;;;
138:05;MRL;Couple Helium coupling;;1;;;;;
138:05;MRL;Couple N2O coupling;;1;;;;;
138:05;MRL;Attach Pneumatic Line to Fueling arm;;1;;;;03:00;
135:05;MRL;Confirm that Ignition Umbilical is disconnected;;1;;;;;
135:05;EGSE;BEGIN EGSE Valve and actuator check Sequence;Valve check;1;;;;;
135:05;MCC;Check if video recording is enabled @ MCC;;1;;;;00:10;
134:55;OBDH;Check EPS hardware;;1;;;;00:10;
134:45;EGSE;Start PID data recording;;1;;;;00:10;
134:35;EGSE;Check OxOutPT 0 Bar;;1;;;;00:10;
134:25;MRL;Close HPNV;;1;;;;00:10;
134:15;EGSE/MRL;Switch OxDV to closed & check if magnetic valve LED is on;;1;;;;00:10;
134:05;EGSE/MRL;Switch HPDV to closed & check if magnetic valve LED is on;;1;;;;00:10;
133:55;EGSE/MRL;Check warning lamp ;;1;;;;00:10;
133:45;MRL;Remove loose equipment;;1;;;;03:00;
130:45;EGSE;Activate Heizi;;1;;;;00:10;
130:35;EGSE;Activate N2O_Heater 1;;1;;;;00:10;
130:25;EGSE;Activate N2O_Heater 2;;1;;;;00:10;
130:15;EGSE;Activate HE_Heater;;1;;;;00:10;
130:05;EGSE;Check OxV1 (CLD & RT_VI);;1;;;;00:10;
129:55;EGSE;Check OxV2 (CLD & RT_VI);;1;;;;00:10;
129:45;EGSE;Check MPV3 (CLD & RT_VI);;1;;;;00:10;
129:35;EGSE;Check HPV1 (CLD & RT_VI);;1;;;;00:10;
129:25;EGSE;Check HPV2 (CLD & RT_VI);;1;;;;00:10;
129:15;EGSE;Check MPV1/2 (CLD & RT_VI);;1;;;;00:10;
129:05;EGSE;Check RDV (CLD & RT_VI);;1;;;;00:10;
128:55;EGSE;Check RMOxOV (CLD & RT_VI);;1;;;;00:10;
128:45;EGSE;Check RMOxSV (CLD & RT_VI);;1;;;;00:10;
128:35;EGSE/MRL;Verify Bottle Temperatures @ OxT1 OxT2 HPT2;;1;;;;00:10;
128:25;EGSE/MRL;Verify Water Temperatures @ Ox@T1 OxWT2 HPWT2;;1;;;;00:10;
128:15;OBDH;Verify Heizi @ RDVT & RDVET;;1;;;;00:10;
128:05;EGSE;Deactivate Heizi;;1;;;;00:10;
127:55;OBDH;Activate Heizi;;1;;;;00:10;
127:45;OBDH;Check RDV;;1;;;;00:10;
127:35;OBDH;Check RNCEV;;1;;;;00:10;
127:25;OBDH;Check RMOxOV;;1;;;;00:10;
127:15;OBDH;Check RMOxSV;;1;;;;00:10;
127:05;OBDH;Confirm RNCEV is disabled;;1;;;;00:10;
126:55;OBDH;Verify Heizi @ RDVT & RDVET;;1;;;;00:10;
126:45;OBDH/TMTC;Check RF451-Link;;1;;;;00:20;
126:25;TMTC;Check GPS-lock;;3;;;;00:20;
126:05;TMTC;Check Telemega-Link;;1;;;;00:20;
125:45;OBDH;Test Connection to STX3;;1;;;;00:20;
125:25;OBDH;Check if STX3 Package received by email;;1;;;;00:30;
124:55;MRL;Check MBV closed;;1;;;;;
124:55;EGSE;Check if all valve switches are in OFF position (Except OxDV & HPDV);;1;;;;10:00;
114:55;MRL/EGSE;Check loadcell by applying force to it;;1;;;;00:20;
114:35;OBDH;Check RHPPT shows atmosphere;;1;;;;;
114:35;OBDH;Check ROxTPT shows atmosphere;;1;;;;;
114:35;OBDH;Check RIHPT shows atmosphere;;1;;;;;
114:35;OBDH;Check RCCPT shows atmosphere;;1;;;;;
114:35;OBDH;Check RBaro1 shows atmosphere;;1;;;;;
114:35;OBDH;Check RBaro2 shows atmosphere;;1;;;;;
114:35;EGSE;Check HPPT1 shows 0 bar;;1;;;;00:20;
114:15;EGSE;Check HPPT2 shows 0 bar;;1;;;;;
114:15;EGSE;Check HPLPT shows 0 bar;;1;;;;;
114:15;EGSE;Check OxInPT1 shows 0 bar;;1;;;;;
114:15;EGSE;Check OxInPT2 shows 0 bar;;1;;;;;
114:15;EGSE;Check OxOutPT shows 0 bar;;1;;;;00:20;
113:55;EGSE/MRL;Switch on N2O coupling & check if magnetic valve LED is on;;1;;;;;
113:55;EGSE/MRL;Switch on HE coupling & check if magnetic valve LED is on;;1;;;;;
113:55;EGSE/MRL;Switch on swivle arm & check if magnetic valve LED is on;;1;;;;;
113:55;EGSE;Switch off swivel arm & HE coupling & N2O coupling;;1;;;;01:00;
112:55;MRL;Confirm that Ignition Umbilical is disconnected;;1;;;;;
112:55;MRL;Connect Ignition test Receptical;;1;;;;;
112:55;EGSE@MRL;Plug in Bridges B1 and B2;;1;;;;;
112:55;MRL;Confirm Soundsignal from Ignition Umbilical;;2;;;;;
112:55;EGSE;Turn on Ignition Secure;;1;;;;;
112:55;EGSE/OBDH;Turn on Ignition Switch for 2 Second & Confirm ignition signal received at sbRio;;1;;;;;
112:55;EGSE;Turn off Ignition Secure;;1;;;;;
112:55;EGSE@MRL;Remove Bridges B1 and B2;;1;;;;;
112:55;MRL;Remove Ignition test Receptical;;1;;;;03:00;
109:55;MCC;Ground Segment Pressure Test (PHASE YELLOW) ;Ground Pressure Test;1;;;;;
109:55;MRL;Confirm that all hatches and covers are closed;;1;;;;01:00;all hatches
108:55;MRL;Check HE bottle 1 connector is attached;;1;;;;;
108:55;MRL;Check HE bottle 2 connector is attached;;1;;;;;
108:55;MRL;Check N2O bottle 1 connector is attached;;1;;;;;
108:55;MRL;Check N2O bottle 2 connector is attached;;1;;;;;
108:55;MRL;Check hose between HPSM & N2OSM is connected on both ends;;1;;;;;
108:55;MRL;Check hose between HPSM & Flight Segment is connected on both ends;;1;;;;;
108:55;MRL;Check hose between N2OSM & Flight Segment is connected on both ends;;1;;;;;
108:55;MRL;Check Pneumatik hose is connected on both ends;;1;;;;02:00;
106:55;MRL;Put on safety equipment;;2;;;;;
106:55;MRL;Move into Position to open HE Bottle 1;;2;;;;;
106:55;MRL;Check if HPV1 is closed;;2;;;;;
106:55;MRL;Check if MPV1/2 is closed;;2;;;;;
106:55;MRL;Open HE Bottle 1;;2;;;;01:00;
105:55;MRL;Check & compare pressure HPPT1 with HPPG1 (max 300 bar);;2;;;;;
105:55;MRL;Check Gastech Silver HPPR1 (max 300 to 50 bar);;2;;;;;
105:55;MRL;Check Harris PPR (50 to 8 bar);;2;;;;;
105:55;MRL;Check pneumatic PPG (8 bar);;2;;;;;
105:55;MRL;Step back;;2;;;;01:00;
104:55;EGSE;Confirm HPPT1 is at 300 Bar;;1;;;;;??
104:55;EGSE;Confirm HPLPT less than 10 Bar;;1;;;;;
104:55;EGSE/MRL;Open & Close HPV1 SHORTLY & Check HPPT1;;2;;;;;
104:55;EGSE/MRL;Open & Close HPV2 SHORTLY & Check HPPT2 0 bar;;2;;;;;
104:55;EGSE/MRL;Open & Close HPDV SHORTLY & Check HPLPT 0 bar;;2;;;;;
104:55;EGSE/MRL;Open & Close OxV1 SHORTLY;;2;;;;;
104:55;EGSE/MRL;Open & Close OxV2 SHORTLY;;2;;;;;
104:55;EGSE/MRL;Open & Close OxDV SHORTLY;;2;;;;;
104:55;EGSE/MRL;Open & Close MPV3 SHORTLY;;2;;;;;
104:55;EGSE;Check HPLPT & OxOutPT 0 Bar;;2;;;;01:30;
103:25;EGSE;Decouple N2O coupling;;2;;;;;
103:25;EGSE;Decouple Helium coupling;;2;;;;00:20;
103:05;EGSE;Move arm away from rocket;;2;;;;;
103:05;EGSE;Move arm to rocket;;2;;;;01:00;
102:05;MRL;Close HE Bottle 1 and check HPSM for leakage (If leakage occurs Abort);;2;;;;01:00;
101:05;MRL;Open HPNV 1/8 Rev;;2;;;;;
101:05;MRL;Open MBV;;2;;;;;
101:05;EGSE/MRL;Check and compare pressure HPPT1 with HPPG1 0 Bar;;2;;;;;
101:05;MRL;Close MBV;;2;;;;00:30;
100:35;MRL;Safety is ensured;;1;;;;;
100:35;MCC;MiS to MRL;;1;;;;;
100:35;EGSE;Switch off N20 coupling;;1;;;;;
100:35;EGSE;Switch off HE coupling;;1;;;;;
100:35;MRL;Release Pneumatic lines;;1;;;;00:20;
100:15;EGSE;Confirm Fueling arm is off;;1;;;;;
100:15;EGSE;Check OxOutPT and HPLPT 0 bar;;1;;;;;
100:15;MRL;Couple Helium coupling;;1;;;;00:30;
99:45;MRL;Couple N2O coupling;;1;;;;00:30;
99:15;MRL;HOLD / RESTART;;1;;;;;
99:15;MRL;BEGIN Arming Rocket SEQUENCE Part 1;Arming 1;1;;;;;
99:15;MRL;Connect Ignition Umbilical;;1;;;;00:30;
98:45;MRL;Turn on GoPro Camera at end of Launch Rail;;1;;;;00:20;
98:25;MRL;Insert EPS Bridges;;1;;;;03:00;
95:25;MRL;Confirm Bridge Hatch is Secured;;1;;;;00:20;
95:05;EGSE@MRL;return to MCC;;1;;;;;
95:05;OPS;Elevate MRL to 90 degrees;;1;;;;05:00;
90:05;EGSE;Powercycle EPS to to start flight mode on Telemega;;1;;;;00:30;
89:35;EGSE;Calibrate loadcell (Set to 0);;1;;;;01:00;
88:35;MCC;BEGIN Pressure Test Flight Segment (PHASE YELLOW) ;Pressure Test Rocket;2;;;;;
88:35;MRL;Put on safety equipment;;2;;;;00:30;
88:05;MRL;Open HE Bottle 1;;2;;;;01:00;
87:05;MRL;Step back;;2;;;;;
87:05;EGSE;Open & Close stepwise MPV1/MPV2 to 50 Bar @ OxInPT1 & OxInPT2;;2;;;;;
87:05;MRL;Check & compare OxInPT1 with OxInPG1 based on Bottle temperature (max 50 bar);;2;;;;;
87:05;MRL;Check & compare pressure OxInPT2 with OxInPG2 based on Bottle temperature (max 50 bar);;2;;;;;
87:05;MRL;Check Temperature of N2O Bottle 1 @OxT1 & OxWT1 (max 22C);;2;;;;;
87:05;MRL;Check Temperature of N2O Bottle 2 @OxT2 & OxWT2 (max 22C);;2;;;;01:30;
85:35;MRL;Open He Bottle 2;;2;;;;;
85:35;MRL;Check & compare pressure HPPT2 with HPPG2 (max 315 bar);;2;;;;01:00;
84:35;ALL;CAUTION!;;2;;;;;
84:35;MRL;Open N2O Bottle 1;;2;;;;;
84:35;MRL/EGSE;Check & compare pressure OxInPT 1 with OxInPG 1 (max 50 bar);;2;;;;02:00;
82:35;MRL;Open N2O Bottle 2;;2;;;;;
82:35;MRL/EGSE;Check & compare pressure OxInPT 2 with OxInPG 2 (max 50 bar);;2;;;;02:00;
80:35;MRL;Insert Ignition Bridges B1 and B2 into EGSE;;2;;;;02:00;
78:35;MRL;Confirm Soundsignal from Ignition Umbilical;;2;;;;;
78:35;MRL;Close ComTerm;;2;;;;;
78:35;ALL;Clear Launchpad and inform OPS;;2;;;;10:00;
68:35;KLP;Start Camera Karsten Lappöhn;;2;;;;;
68:35;MCC;HOLD / RESTART;HOLD / RESTART;2;;;;;
68:35;MCC;Begin of Ox FUELING Sequence (PHASE RED);Ox Fueling (PHASE RED);3;;;;;
68:35;TMTC;Confirm GPS-lock;;3;;;;;
68:35;OBDH;Acknowledge start of Fueling;;3;;;;01:00;CHANGE to 3 steps
67:35;EGSE;Open & Close HPV1 to 50 Bar @ ROxTPT (stop at 30 bar and wait 30 seconds to check for leakage);;3;;;;;
67:35;EGSE;Open & Close HPV1 to more than 50 Bar @ RHPPT and check ROxTPT 50 Bar;;3;;;;;
67:35;EGSE;Check if HPV1 is closed;;3;;;;;
67:35;OBDH;Open RDV shortly, to check tightness @ RHPPT & ROxTPT (If leakages occur Abort);;3;;;;;
67:35;EGSE;Open MPV1/MPV2;;3;;;;;
67:35;EGSE;Open & Close stepwise MPV3 to 50 Bar @ OxOutPT;;3;;;;;
67:35;EGSE;Close MPV1/MPV2;;3;;;;;
67:35;EGSE;Check & compare OxOutPT with OxInPT1;;3;;;;;
67:35;EGSE;Check if RHPPT & ROxTPT more than OxInPT1, If less Open & Close HPV1;;3;;;;;
67:35;EGSE;Zero OxTank Mass;;3;;;;;
67:35;MCC;Write down Time;;3;;;;;
67:35;EGSE;Open OxV1 ;;3;;;;04:00;
63:35;OBDH;Open stepwise RDV until N2O bottle empty or 25kg OxTankMass, keep temperatures RDVT and RDVET above 10°C and Check delta ROxTPT and OxInPT1;;3;;;;30:00;
33:35;EGSE;Close OxV1;;3;;;;00:10;
33:25;EGSE;Check if Pressure rises in OxPT1, if Pressure rises relief via OxV1 or wait for Pressure relief valve;;3;;;;01:00;
32:25;EGSE;Check & compare OxOutPT with OxInPT2;;3;;;;;
32:25;EGSE;Check & compare RHPPT & ROxTPT 50 Bar and more than OxInPT2, If less Open & Close HPV1;;3;;;;;
32:25;EGSE;Open OxV2 ;;3;;;;;
32:25;OBDH;Open stepwise RDV to 25kg OxTankMass, keep temperatures RDVT and RDVET above 10°C and Check delta OxTPT and OxInPT1;;3;;;;20:00;
12:25;EGSE;Close OxV2 ;;3;;;;00:10;
12:15;EGSE;Check if Pressure rises in OxPT2, if Pressure rises relief via OxV2 or wait for Pressure relief valve;;3;;;;01:00;
11:15;EGSE;Open stepwise OxDV until OxOutPT 0 Bar;;3;;;;;
11:15;OBDH;Check ROxCV for tightness @ ROxTPT;;3;;;;;
11:15;EGSE;Close OxDV;;3;;;;01:00;
10:15;EGSE;Write down OxTankMass;;3;;;;;
10:15;MCC;Provied OxTankMass and Temperature Readings to Windwaiting Station;;3;;;;00:30;
09:45;EGSE;Confirm OxV1 & OxV2 closed;;3;;;;;
09:45;EGSE;Check OxOutPT 0 Bar;;3;;;;;
09:45;EGSE;Decouple N2O coupling;;3;;;;00:20;
09:25;MCC;Confirm End of Oxidator Fueling to OPS;;3;;;;00:15;
09:10;OBDH/TMTC;Check RF451-Link;;3;;;;00:20;
08:50;TMTC;Check GPS-lock;;3;;;;00:20;
08:30;TMTC;Check Telemega-Link;;3;;;;00:20;
08:10;MCC;Scheduled HOLD;;3;;;;;
08:10;ALL;Align MRL to Launch Trajectory;;3;;;;;
08:10;MCC;Confirm MRL adjustment is final;;3;;;;;
08:10;ALL;Talk through Launch Sequence;;3;;;;;
08:10;AVC;Start Video Recording in BlockHouse;;3;;;;;
08:10;MCC;Turn audio volume down;;3;;;;;
08:10;MCC;CONTINUE AFTER HOLD;;;;;;;
08:10;MCC;BEGIN Switching to Internal Power Sequence;Switch to Internal Power;3;;;;;
08:10;EGSE;Switch to internal Power;;3;;;;00:20;
07:50;OBDH;Confirm EPS Voltages are within limits;;3;;;;00:10;
07:45;OBDH;Confirm RF451 Transmitting;;3;;;;00:05;
07:20;OBDH/TMTC;Confirm RF451-Link;;3;;;;00:20;
07:40;TMTC;Confirm GPS-lock;;3;;;;00:20;
07:00;TMTC;Confirm Telemega-Link;;3;;;;00:20;
06:40;OBDH;Switch to PREAMRED;;3;;;;00:10;
06:30;PYL;Confirm Payload is running;;3;;;;00:20;
06:10;AVC;Check if videorecording @ MCC is running;;3;;;;00:05;
06:05;MCC;High Pressure Fuling;HP Fueling;3;;;;;
06:05;EGSE;Open and close HPV1 stepwise until RHPPT 300 Bar or pressure equal to HE Bottle 1;;3;;;;;
06:05;EGSE;Open and close HPV2 stepwise until RHPPT 300 Bar ;;3;;;;;
06:05;EGSE;Open and close HPDV stepwise until HPLPT 0 Bar ;;3;;;;;
06:05;EGSE;Check HPDV closed;;3;;;;;
06:05;OBDH/EGSE;Check for leakage HPLPT 0 Bar & RHPPT 300 Bar ;;3;;;;02:00;
04:05;OBDH;Acknowledge end of Fueling;;3;;;;00:10;
03:55;MCC;Confirm End of Fueling to OPS;;3;;;;00:20;
03:35;MCC;BEGIN of Moving Fueling Arm Away Sequence;Move Fueling Arm away;3;;;;00:10;
03:25;EGSE;Confirm HPV1 & HPV2 closed;;3;;;;00:10;
03:15;EGSE;Check HPLPT 0 Bar ;;3;;;;00:10;
03:05;EGSE;Decouple Helium coupling;;3;;;;00:20;
02:45;EGSE;Confirm Helium coupling is disconnected;;3;;;;00:10;
02:35;EGSE;Move fueling arm away from rocket;;3;;;;00:40;
01:55;MCC;Confirm Fueling Arm away to OPS;;3;;;;00:15;
01:40;MCC;Prepare for Launch;;3;;;;00:10;
01:30;OBDH;Confirm ready for launch;;3;;;;00:10;
01:20;EGSE;Confirm ready for launch;;3;;;;00:10;
01:10;MCC;Set Go/No-Go System to Go;;3;;;;00:10;
01:00;MCC;Wait for Authorization for Launch;;3;;;;00:00;
01:00;MCC;BEGIN of Ignition Sequence;Ignition Sequence;4;;;;00:10;
00:50;OBDH;ARM;;4;;;;00:05;
00:45;OBDH;Confirm all status indicators green;;4;;;;00:05;
00:40;OBDH;Ethernet Disconnect;;4;;;;00:30;
00:10;EGSE;Turn on Ignition Secure;;4;;;;00:07;
00:03;EGSE;T-3: Ignition;;4;;;;00:03;
00:00;OBDH;T+0: Verify RMOxOV Open (Launched);;4;;;;00:00;
00:00;EGSE;T+1: Turn OFF Ignition;;4;;;;;
00:00;EGSE;T+5: Turn OFF Ignition Secure;;4;;;;;
00:00;OBDH;T+20: Verify RMOxOV Closed and RMOxSV Open (Cruise);;4;;;;;
00:00;OBDH;T+50: Verify RNCEV Open (Drogue);;4;;;;;
00:00;OBDH;T+310: Verify Main Chute Deployed and RDV Open (Main);;4;;;;;
00:00;OBDH;T+600: Verify (Landed);;4;;;;;
00:00;MCC;START OF PASSIVATION (PHASE YELLOW) (Write down Time);Passivation;2;;;;;
00:00;MCC;Turn audio volume up;;2;;;;;
00:00;TMTC;Check ROxTPT & RHPPT 1 Bar, if more: Open & Close stepwise RDV;;2;;;;;
00:00;MRL;Go to Testrig, close N2O Bottle 1 & N2O Bottle 2 and return to BlockHouse;;2;;;;;
00:00;EGSE;Open OxDV;;2;;;;;
00:00;EGSE;Open OxV1;;2;;;;;
00:00;EGSE;Check OxInPT1 & OxOutPT 0 Bar;;2;;;;;
00:00;EGSE;Close OxV1;;2;;;;;
00:00;EGSE;Open OxV2;;2;;;;;
00:00;EGSE;Check OxInPT2 & OxOutPT 0 Bar;;2;;;;;
00:00;EGSE;Close OxV2;;2;;;;;
00:00;EGSE;Close OxDV ;;2;;;;;
00:00;MRL;Go to MRL, confirm OxInPG1 & OxInPG2 0 Bar, else return to BlockHouse, then close HE Bottle;;2;;;;;
00:00;MRL;Write down remaining Pressure of HE Bottle;;2;;;;;
00:00;EGSE;Open HPDV;;2;;;;;
00:00;EGSE;Open HPV2;;2;;;;;
00:00;EGSE;Check pressure HPLPT & HPPT2 0 Bar;;2;;;;;
00:00;EGSE;Close HPV2;;2;;;;;
00:00;EGSE;Close HPDV;;2;;;;;
00:00;MRL;Go to Testrig, confirm HPPG2 0 Bar, else return to BlockHouse, then open ComTerm;;2;;;;;
12960:00;MRL;Close N2 Bottle;;2;;;;;
00:00;MRL;Write down remaining Pressure of N2 Bottle;;2;;;;;
00:00;MRL;Step back;;2;;;;;
00:00;MRL;Check EPV manometer less than 6 bar;;2;;;;;
00:00;MRL;Open MBV;;2;;;;;
00:00;EGSE;Check and compare pressure HPPT1 with HPPG1;;2;;;;;
00:00;MRL;Close MBV;;2;;;;;
00:00;MRL;Take out B1 & B2 Bridges;;2;;;;;
00:00;MRL;Safety is ensured;;2;;;;;
00:00;MCC;Turn off area warning light and open barrier;;1;;;;;
00:00;MCC;END OF PASSIVATION (PHASE GREEN) (Write down Time);;1;;;;;
00:00;MCC;START DATA COLLECTION (Write down Time);Collection;1;;;;;
00:00;AVC;Turn off GoPro & Camcorder & Stop BlockHouse Video recording;;1;;;;;
00:00;EGSE;Copy PID.vi.tdms & save to new name;;1;;;;;
00:00;EGSE;Wait for buffer storage process to be finished;;1;;;;;
00:00;EGSE;save data files from cRIO to PC;;1;;;;;
00:00;AVC;End audio recording;;1;;;;;
00:00;MCC;END OF PROCEDURE (Write Down Time);;1;;;;;
00:00;AVC;Save video & audio data on external HDD;;1;;;;;
00:00;MCC;Stop RT_CD.vi and save logfile to external HDD;;1;;;;;
00:00;MCC;PROCEDURE FINISHED;End;1;;;;;
1 vers. v3.0 Launch Procedure 0 MRL MCC Radar Hill Time per step
2 148:35 EGSE Check CLD connection 1
3 148:35 EGSE Switch on CLD via Battery & check voltage (24 Volt) 1
4 148:35 EGSE Switch on the primary and secondary supply switches on the Control Panel 1 01:00
5 147:35 EGSE Power on EGSE Power on EGSE 1
6 147:35 EGSE@MRL Switch on Sup_24V_20A & check voltage (ca. 27,2 Volt) 1
7 147:35 EGSE@MRL Switch on Sup_24V_10A & check voltage (ca. 27,2 Volt) 1
8 147:35 EGSE@MRL Switch on Sup_12V_10A & check voltage (ca. 13,8 Volt) 1
9 147:35 EGSE@MRL Switch on Bat_24V_20A & check voltage (ca. 27,9 Volt) 1
10 147:35 EGSE@MRL Switch on Bat_24V_10A & check voltage (ca. 27,9 Volt) 1
11 147:35 EGSE@MRL Switch on Bat_12V_10A & check voltage (ca. 13,8 Volt) 1
12 147:35 EGSE@MRL Switch on Sup_24V_40A 1
13 147:35 EGSE@MRL Switch on Sup_5V_10A 1 03:00
14 144:35 EGSE Connect to cRIO 1
15 144:35 EGSE Start FPGA_VI 1
16 144:35 EGSE Start RT_VI 1
17 144:35 EGSE Confirm PID-VI is running 1
18 144:35 EGSE Rename PID-Logfile 1 02:00
19 142:35 MRL Confirm working Personel is grounded 1
20 142:35 MRL Connect Data Umbilical Connect Data Umbilical 1 00:30
21 142:05 EGSE Start EPS via EPS_ext 1
22 142:05 EGSE@MRL Set Fuse in Power supply control panel 1
23 142:05 EGSE@MRL Insert EPS_bat Bridge 1 02:00
24 140:05 OBDH Clear SD-Card-using FileZilla FTP 01:00
25 139:05 OBDH Connect to sbRIO 1
26 139:05 OBDH Start RT_Main 1
27 139:05 MRL Confirm 3 beeps at OBC1 1
28 139:05 OBDH Open RT_Sub_HMI 1
29 139:05 OBDH Confirm Main Chute button is disabled 1
30 139:05 MRL Confirm working Personel is grounded 1 01:00
31 138:05 MRL Remove Pneumatic Line from Fueling arm 1
32 138:05 MRL Move Fueling arm to rocket 1
33 138:05 MRL Couple Helium coupling 1
34 138:05 MRL Couple N2O coupling 1
35 138:05 MRL Attach Pneumatic Line to Fueling arm 1 03:00
36 135:05 MRL Confirm that Ignition Umbilical is disconnected 1
37 135:05 EGSE BEGIN EGSE Valve and actuator check Sequence Valve check 1
38 135:05 MCC Check if video recording is enabled @ MCC 1 00:10
39 134:55 OBDH Check EPS hardware 1 00:10
40 134:45 EGSE Start PID data recording 1 00:10
41 134:35 EGSE Check OxOutPT 0 Bar 1 00:10
42 134:25 MRL Close HPNV 1 00:10
43 134:15 EGSE/MRL Switch OxDV to closed & check if magnetic valve LED is on 1 00:10
44 134:05 EGSE/MRL Switch HPDV to closed & check if magnetic valve LED is on 1 00:10
45 133:55 EGSE/MRL Check warning lamp 1 00:10
46 133:45 MRL Remove loose equipment 1 03:00
47 130:45 EGSE Activate Heizi 1 00:10
48 130:35 EGSE Activate N2O_Heater 1 1 00:10
49 130:25 EGSE Activate N2O_Heater 2 1 00:10
50 130:15 EGSE Activate HE_Heater 1 00:10
51 130:05 EGSE Check OxV1 (CLD & RT_VI) 1 00:10
52 129:55 EGSE Check OxV2 (CLD & RT_VI) 1 00:10
53 129:45 EGSE Check MPV3 (CLD & RT_VI) 1 00:10
54 129:35 EGSE Check HPV1 (CLD & RT_VI) 1 00:10
55 129:25 EGSE Check HPV2 (CLD & RT_VI) 1 00:10
56 129:15 EGSE Check MPV1/2 (CLD & RT_VI) 1 00:10
57 129:05 EGSE Check RDV (CLD & RT_VI) 1 00:10
58 128:55 EGSE Check RMOxOV (CLD & RT_VI) 1 00:10
59 128:45 EGSE Check RMOxSV (CLD & RT_VI) 1 00:10
60 128:35 EGSE/MRL Verify Bottle Temperatures @ OxT1 OxT2 HPT2 1 00:10
61 128:25 EGSE/MRL Verify Water Temperatures @ Ox@T1 OxWT2 HPWT2 1 00:10
62 128:15 OBDH Verify Heizi @ RDVT & RDVET 1 00:10
63 128:05 EGSE Deactivate Heizi 1 00:10
64 127:55 OBDH Activate Heizi 1 00:10
65 127:45 OBDH Check RDV 1 00:10
66 127:35 OBDH Check RNCEV 1 00:10
67 127:25 OBDH Check RMOxOV 1 00:10
68 127:15 OBDH Check RMOxSV 1 00:10
69 127:05 OBDH Confirm RNCEV is disabled 1 00:10
70 126:55 OBDH Verify Heizi @ RDVT & RDVET 1 00:10
71 126:45 OBDH/TMTC Check RF451-Link 1 00:20
72 126:25 TMTC Check GPS-lock 3 00:20
73 126:05 TMTC Check Telemega-Link 1 00:20
74 125:45 OBDH Test Connection to STX3 1 00:20
75 125:25 OBDH Check if STX3 Package received by email 1 00:30
76 124:55 MRL Check MBV closed 1
77 124:55 EGSE Check if all valve switches are in OFF position (Except OxDV & HPDV) 1 10:00
78 114:55 MRL/EGSE Check loadcell by applying force to it 1 00:20
79 114:35 OBDH Check RHPPT shows atmosphere 1
80 114:35 OBDH Check ROxTPT shows atmosphere 1
81 114:35 OBDH Check RIHPT shows atmosphere 1
82 114:35 OBDH Check RCCPT shows atmosphere 1
83 114:35 OBDH Check RBaro1 shows atmosphere 1
84 114:35 OBDH Check RBaro2 shows atmosphere 1
85 114:35 EGSE Check HPPT1 shows 0 bar 1 00:20
86 114:15 EGSE Check HPPT2 shows 0 bar 1
87 114:15 EGSE Check HPLPT shows 0 bar 1
88 114:15 EGSE Check OxInPT1 shows 0 bar 1
89 114:15 EGSE Check OxInPT2 shows 0 bar 1
90 114:15 EGSE Check OxOutPT shows 0 bar 1 00:20
91 113:55 EGSE/MRL Switch on N2O coupling & check if magnetic valve LED is on 1
92 113:55 EGSE/MRL Switch on HE coupling & check if magnetic valve LED is on 1
93 113:55 EGSE/MRL Switch on swivle arm & check if magnetic valve LED is on 1
94 113:55 EGSE Switch off swivel arm & HE coupling & N2O coupling 1 01:00
95 112:55 MRL Confirm that Ignition Umbilical is disconnected 1
96 112:55 MRL Connect Ignition test Receptical 1
97 112:55 EGSE@MRL Plug in Bridges B1 and B2 1
98 112:55 MRL Confirm Soundsignal from Ignition Umbilical 2
99 112:55 EGSE Turn on Ignition Secure 1
100 112:55 EGSE/OBDH Turn on Ignition Switch for 2 Second & Confirm ignition signal received at sbRio 1
101 112:55 EGSE Turn off Ignition Secure 1
102 112:55 EGSE@MRL Remove Bridges B1 and B2 1
103 112:55 MRL Remove Ignition test Receptical 1 03:00
104 109:55 MCC Ground Segment Pressure Test (PHASE YELLOW) Ground Pressure Test 1
105 109:55 MRL Confirm that all hatches and covers are closed 1 01:00 all hatches
106 108:55 MRL Check HE bottle 1 connector is attached 1
107 108:55 MRL Check HE bottle 2 connector is attached 1
108 108:55 MRL Check N2O bottle 1 connector is attached 1
109 108:55 MRL Check N2O bottle 2 connector is attached 1
110 108:55 MRL Check hose between HPSM & N2OSM is connected on both ends 1
111 108:55 MRL Check hose between HPSM & Flight Segment is connected on both ends 1
112 108:55 MRL Check hose between N2OSM & Flight Segment is connected on both ends 1
113 108:55 MRL Check Pneumatik hose is connected on both ends 1 02:00
114 106:55 MRL Put on safety equipment 2
115 106:55 MRL Move into Position to open HE Bottle 1 2
116 106:55 MRL Check if HPV1 is closed 2
117 106:55 MRL Check if MPV1/2 is closed 2
118 106:55 MRL Open HE Bottle 1 2 01:00
119 105:55 MRL Check & compare pressure HPPT1 with HPPG1 (max 300 bar) 2
120 105:55 MRL Check Gastech Silver HPPR1 (max 300 to 50 bar) 2
121 105:55 MRL Check Harris PPR (50 to 8 bar) 2
122 105:55 MRL Check pneumatic PPG (8 bar) 2
123 105:55 MRL Step back 2 01:00
124 104:55 EGSE Confirm HPPT1 is at 300 Bar 1 ??
125 104:55 EGSE Confirm HPLPT less than 10 Bar 1
126 104:55 EGSE/MRL Open & Close HPV1 SHORTLY & Check HPPT1 2
127 104:55 EGSE/MRL Open & Close HPV2 SHORTLY & Check HPPT2 0 bar 2
128 104:55 EGSE/MRL Open & Close HPDV SHORTLY & Check HPLPT 0 bar 2
129 104:55 EGSE/MRL Open & Close OxV1 SHORTLY 2
130 104:55 EGSE/MRL Open & Close OxV2 SHORTLY 2
131 104:55 EGSE/MRL Open & Close OxDV SHORTLY 2
132 104:55 EGSE/MRL Open & Close MPV3 SHORTLY 2
133 104:55 EGSE Check HPLPT & OxOutPT 0 Bar 2 01:30
134 103:25 EGSE Decouple N2O coupling 2
135 103:25 EGSE Decouple Helium coupling 2 00:20
136 103:05 EGSE Move arm away from rocket 2
137 103:05 EGSE Move arm to rocket 2 01:00
138 102:05 MRL Close HE Bottle 1 and check HPSM for leakage (If leakage occurs Abort) 2 01:00
139 101:05 MRL Open HPNV 1/8 Rev 2
140 101:05 MRL Open MBV 2
141 101:05 EGSE/MRL Check and compare pressure HPPT1 with HPPG1 0 Bar 2
142 101:05 MRL Close MBV 2 00:30
143 100:35 MRL Safety is ensured 1
144 100:35 MCC MiS to MRL 1
145 100:35 EGSE Switch off N20 coupling 1
146 100:35 EGSE Switch off HE coupling 1
147 100:35 MRL Release Pneumatic lines 1 00:20
148 100:15 EGSE Confirm Fueling arm is off 1
149 100:15 EGSE Check OxOutPT and HPLPT 0 bar 1
150 100:15 MRL Couple Helium coupling 1 00:30
151 99:45 MRL Couple N2O coupling 1 00:30
152 99:15 MRL HOLD / RESTART 1
153 99:15 MRL BEGIN Arming Rocket SEQUENCE Part 1 Arming 1 1
154 99:15 MRL Connect Ignition Umbilical 1 00:30
155 98:45 MRL Turn on GoPro Camera at end of Launch Rail 1 00:20
156 98:25 MRL Insert EPS Bridges 1 03:00
157 95:25 MRL Confirm Bridge Hatch is Secured 1 00:20
158 95:05 EGSE@MRL return to MCC 1
159 95:05 OPS Elevate MRL to 90 degrees 1 05:00
160 90:05 EGSE Powercycle EPS to to start flight mode on Telemega 1 00:30
161 89:35 EGSE Calibrate loadcell (Set to 0) 1 01:00
162 88:35 MCC BEGIN Pressure Test Flight Segment (PHASE YELLOW) Pressure Test Rocket 2
163 88:35 MRL Put on safety equipment 2 00:30
164 88:05 MRL Open HE Bottle 1 2 01:00
165 87:05 MRL Step back 2
166 87:05 EGSE Open & Close stepwise MPV1/MPV2 to 50 Bar @ OxInPT1 & OxInPT2 2
167 87:05 MRL Check & compare OxInPT1 with OxInPG1 based on Bottle temperature (max 50 bar) 2
168 87:05 MRL Check & compare pressure OxInPT2 with OxInPG2 based on Bottle temperature (max 50 bar) 2
169 87:05 MRL Check Temperature of N2O Bottle 1 @OxT1 & OxWT1 (max 22C) 2
170 87:05 MRL Check Temperature of N2O Bottle 2 @OxT2 & OxWT2 (max 22C) 2 01:30
171 85:35 MRL Open He Bottle 2 2
172 85:35 MRL Check & compare pressure HPPT2 with HPPG2 (max 315 bar) 2 01:00
173 84:35 ALL CAUTION! 2
174 84:35 MRL Open N2O Bottle 1 2
175 84:35 MRL/EGSE Check & compare pressure OxInPT 1 with OxInPG 1 (max 50 bar) 2 02:00
176 82:35 MRL Open N2O Bottle 2 2
177 82:35 MRL/EGSE Check & compare pressure OxInPT 2 with OxInPG 2 (max 50 bar) 2 02:00
178 80:35 MRL Insert Ignition Bridges B1 and B2 into EGSE 2 02:00
179 78:35 MRL Confirm Soundsignal from Ignition Umbilical 2
180 78:35 MRL Close ComTerm 2
181 78:35 ALL Clear Launchpad and inform OPS 2 10:00
182 68:35 KLP Start Camera Karsten Lapphn 2
183 68:35 MCC HOLD / RESTART HOLD / RESTART 2
184 68:35 MCC Begin of Ox FUELING Sequence (PHASE RED) Ox Fueling (PHASE RED) 3
185 68:35 TMTC Confirm GPS-lock 3
186 68:35 OBDH Acknowledge start of Fueling 3 01:00 CHANGE to 3 steps
187 67:35 EGSE Open & Close HPV1 to 50 Bar @ ROxTPT (stop at 30 bar and wait 30 seconds to check for leakage) 3
188 67:35 EGSE Open & Close HPV1 to more than 50 Bar @ RHPPT and check ROxTPT 50 Bar 3
189 67:35 EGSE Check if HPV1 is closed 3
190 67:35 OBDH Open RDV shortly, to check tightness @ RHPPT & ROxTPT (If leakages occur Abort) 3
191 67:35 EGSE Open MPV1/MPV2 3
192 67:35 EGSE Open & Close stepwise MPV3 to 50 Bar @ OxOutPT 3
193 67:35 EGSE Close MPV1/MPV2 3
194 67:35 EGSE Check & compare OxOutPT with OxInPT1 3
195 67:35 EGSE Check if RHPPT & ROxTPT more than OxInPT1, If less Open & Close HPV1 3
196 67:35 EGSE Zero OxTank Mass 3
197 67:35 MCC Write down Time 3
198 67:35 EGSE Open OxV1 3 04:00
199 63:35 OBDH Open stepwise RDV until N2O bottle empty or 25kg OxTankMass, keep temperatures RDVT and RDVET above 10C and Check delta ROxTPT and OxInPT1 3 30:00
200 33:35 EGSE Close OxV1 3 00:10
201 33:25 EGSE Check if Pressure rises in OxPT1, if Pressure rises relief via OxV1 or wait for Pressure relief valve 3 01:00
202 32:25 EGSE Check & compare OxOutPT with OxInPT2 3
203 32:25 EGSE Check & compare RHPPT & ROxTPT 50 Bar and more than OxInPT2, If less Open & Close HPV1 3
204 32:25 EGSE Open OxV2 3
205 32:25 OBDH Open stepwise RDV to 25kg OxTankMass, keep temperatures RDVT and RDVET above 10C and Check delta OxTPT and OxInPT1 3 20:00
206 12:25 EGSE Close OxV2 3 00:10
207 12:15 EGSE Check if Pressure rises in OxPT2, if Pressure rises relief via OxV2 or wait for Pressure relief valve 3 01:00
208 11:15 EGSE Open stepwise OxDV until OxOutPT 0 Bar 3
209 11:15 OBDH Check ROxCV for tightness @ ROxTPT 3
210 11:15 EGSE Close OxDV 3 01:00
211 10:15 EGSE Write down OxTankMass 3
212 10:15 MCC Provied OxTankMass and Temperature Readings to Windwaiting Station 3 00:30
213 09:45 EGSE Confirm OxV1 & OxV2 closed 3
214 09:45 EGSE Check OxOutPT 0 Bar 3
215 09:45 EGSE Decouple N2O coupling 3 00:20
216 09:25 MCC Confirm End of Oxidator Fueling to OPS 3 00:15
217 09:10 OBDH/TMTC Check RF451-Link 3 00:20
218 08:50 TMTC Check GPS-lock 3 00:20
219 08:30 TMTC Check Telemega-Link 3 00:20
220 08:10 MCC Scheduled HOLD 3
221 08:10 ALL Align MRL to Launch Trajectory 3
222 08:10 MCC Confirm MRL adjustment is final 3
223 08:10 ALL Talk through Launch Sequence 3
224 08:10 AVC Start Video Recording in BlockHouse 3
225 08:10 MCC Turn audio volume down 3
226 08:10 MCC CONTINUE AFTER HOLD
227 08:10 MCC BEGIN Switching to Internal Power Sequence Switch to Internal Power 3
228 08:10 EGSE Switch to internal Power 3 00:20
229 07:50 OBDH Confirm EPS Voltages are within limits 3 00:10
230 07:45 OBDH Confirm RF451 Transmitting 3 00:05
231 07:20 OBDH/TMTC Confirm RF451-Link 3 00:20
232 07:40 TMTC Confirm GPS-lock 3 00:20
233 07:00 TMTC Confirm Telemega-Link 3 00:20
234 06:40 OBDH Switch to PREAMRED 3 00:10
235 06:30 PYL Confirm Payload is running 3 00:20
236 06:10 AVC Check if videorecording @ MCC is running 3 00:05
237 06:05 MCC High Pressure Fuling HP Fueling 3
238 06:05 EGSE Open and close HPV1 stepwise until RHPPT 300 Bar or pressure equal to HE Bottle 1 3
239 06:05 EGSE Open and close HPV2 stepwise until RHPPT 300 Bar 3
240 06:05 EGSE Open and close HPDV stepwise until HPLPT 0 Bar 3
241 06:05 EGSE Check HPDV closed 3
242 06:05 OBDH/EGSE Check for leakage HPLPT 0 Bar & RHPPT 300 Bar 3 02:00
243 04:05 OBDH Acknowledge end of Fueling 3 00:10
244 03:55 MCC Confirm End of Fueling to OPS 3 00:20
245 03:35 MCC BEGIN of Moving Fueling Arm Away Sequence Move Fueling Arm away 3 00:10
246 03:25 EGSE Confirm HPV1 & HPV2 closed 3 00:10
247 03:15 EGSE Check HPLPT 0 Bar 3 00:10
248 03:05 EGSE Decouple Helium coupling 3 00:20
249 02:45 EGSE Confirm Helium coupling is disconnected 3 00:10
250 02:35 EGSE Move fueling arm away from rocket 3 00:40
251 01:55 MCC Confirm Fueling Arm away to OPS 3 00:15
252 01:40 MCC Prepare for Launch 3 00:10
253 01:30 OBDH Confirm ready for launch 3 00:10
254 01:20 EGSE Confirm ready for launch 3 00:10
255 01:10 MCC Set Go/No-Go System to Go 3 00:10
256 01:00 MCC Wait for Authorization for Launch 3 00:00
257 01:00 MCC BEGIN of Ignition Sequence Ignition Sequence 4 00:10
258 00:50 OBDH ARM 4 00:05
259 00:45 OBDH Confirm all status indicators green 4 00:05
260 00:40 OBDH Ethernet Disconnect 4 00:30
261 00:10 EGSE Turn on Ignition Secure 4 00:07
262 00:03 EGSE T-3: Ignition 4 00:03
263 00:00 OBDH T+0: Verify RMOxOV Open (Launched) 4 00:00
264 00:00 EGSE T+1: Turn OFF Ignition 4
265 00:00 EGSE T+5: Turn OFF Ignition Secure 4
266 00:00 OBDH T+20: Verify RMOxOV Closed and RMOxSV Open (Cruise) 4
267 00:00 OBDH T+50: Verify RNCEV Open (Drogue) 4
268 00:00 OBDH T+310: Verify Main Chute Deployed and RDV Open (Main) 4
269 00:00 OBDH T+600: Verify (Landed) 4
270 00:00 MCC START OF PASSIVATION (PHASE YELLOW) (Write down Time) Passivation 2
271 00:00 MCC Turn audio volume up 2
272 00:00 TMTC Check ROxTPT & RHPPT 1 Bar, if more: Open & Close stepwise RDV 2
273 00:00 MRL Go to Testrig, close N2O Bottle 1 & N2O Bottle 2 and return to BlockHouse 2
274 00:00 EGSE Open OxDV 2
275 00:00 EGSE Open OxV1 2
276 00:00 EGSE Check OxInPT1 & OxOutPT 0 Bar 2
277 00:00 EGSE Close OxV1 2
278 00:00 EGSE Open OxV2 2
279 00:00 EGSE Check OxInPT2 & OxOutPT 0 Bar 2
280 00:00 EGSE Close OxV2 2
281 00:00 EGSE Close OxDV 2
282 00:00 MRL Go to MRL, confirm OxInPG1 & OxInPG2 0 Bar, else return to BlockHouse, then close HE Bottle 2
283 00:00 MRL Write down remaining Pressure of HE Bottle 2
284 00:00 EGSE Open HPDV 2
285 00:00 EGSE Open HPV2 2
286 00:00 EGSE Check pressure HPLPT & HPPT2 0 Bar 2
287 00:00 EGSE Close HPV2 2
288 00:00 EGSE Close HPDV 2
289 00:00 MRL Go to Testrig, confirm HPPG2 0 Bar, else return to BlockHouse, then open ComTerm 2
290 12960:00 MRL Close N2 Bottle 2
291 00:00 MRL Write down remaining Pressure of N2 Bottle 2
292 00:00 MRL Step back 2
293 00:00 MRL Check EPV manometer less than 6 bar 2
294 00:00 MRL Open MBV 2
295 00:00 EGSE Check and compare pressure HPPT1 with HPPG1 2
296 00:00 MRL Close MBV 2
297 00:00 MRL Take out B1 & B2 Bridges 2
298 00:00 MRL Safety is ensured 2
299 00:00 MCC Turn off area warning light and open barrier 1
300 00:00 MCC END OF PASSIVATION (PHASE GREEN) (Write down Time) 1
301 00:00 MCC START DATA COLLECTION (Write down Time) Collection 1
302 00:00 AVC Turn off GoPro & Camcorder & Stop BlockHouse Video recording 1
303 00:00 EGSE Copy PID.vi.tdms & save to new name 1
304 00:00 EGSE Wait for buffer storage process to be finished 1
305 00:00 EGSE save data files from cRIO to PC 1
306 00:00 AVC End audio recording 1
307 00:00 MCC END OF PROCEDURE (Write Down Time) 1
308 00:00 AVC Save video & audio data on external HDD 1
309 00:00 MCC Stop RT_CD.vi and save logfile to external HDD 1
310 00:00 MCC PROCEDURE FINISHED End 1