1vers.v4.22Passivation out of sequence Procedure2
20:00MCCBEGIN SEQUENCE: Prepare Passivation SequencePrepare Passivation2
30:00MCC/MRLRecall and make sure BOTH N2O Bottles & He Bottle 2 are still closed! Else continue with Abort Procedure2
40:00MCCInform OPS of Passivation out of sequence2
50:00MRLStep Back/Leave MRL2
60:00EGSEConfirm all valve switches are in OFF position (Except OxDV & HPDV)2
70:00OBDHConfirm all valve switches are in OFF position (Except RMOxSV)2
80:00MCCBEGIN SEQUENCE: Passivation of GSEPassivation of GSE2
90:00EGSEOpen & Close OxDV STEPWISE until OxOutPT 0 Bar2
100:00EGSEOpen OxDV2
110:00EGSEOpen MPV32
120:00EGSEConfirm OxOutPT 0 bar2
130:00EGSEClose MPV32
140:00EGSEOpen OxV12
150:00EGSEConfirm OxInPT1 & OxOutPT 0 Bar2
160:00EGSEClose OxV12
170:00EGSEOpen OxV22
180:00EGSEConfirm OxInPT2 & OxOutPT 0 Bar2
190:00EGSEClose OxV22
200:00EGSEClose OxDV 2
210:00EGSEOpen HPDV2
220:00EGSEConfirm HPLPT 0 bar2
230:00EGSEOpen HPV22
240:00EGSEConfirm HPLPT & HPPT2 0 bar2
250:00EGSEClose HPV22
260:00EGSEClose HPDV2
270:00MCCBEGIN:Passivation of RocketPassivation of Rocket2
280:00OBDHOpen & Close stepwise RDV until RHPPT & ROxTPT 1 Bar2
290:00OBDHConfirm RHPPT & ROxTPT 1 Bar2
300:00MRLGo to MRL2
310:00MRLRemove HP section maintenance cover2
320:00MRLOpen RMDV & Step Back, Wait until NCE-Tank is pressureless2
330:00MCCBEGIN SEQUENCE: Finish PassivationFinish Passivation2
340:00MRLGo to MRL2
350:00MRLClose He Bottle 12
360:00MCC/MRLWrite down remaining Pressure of He Bottle 12
370:00MRLStep back2
380:00EGSEOpen HPDV2
390:00EGSEOpen HPV12
400:00EGSEConfirm HPLPT & HPPT1 0 Bar2
410:00EGSEClose HPV12
420:00EGSEClose HPDV2
430:00EGSEPressure Check2
440:00MRLOpen MBV2
450:00EGSE/ MRLCheck and compare pressure HPPT1 with HPPG12
460:00MRLClose MBV2
470:00MRLSafety is ensured2
480:00MCCConfirm to OPS that Safety is ensured1
490:00MCCEND OF PROCEDURE1