1vers.v4.23Launch Procedure0MRLMCCRdHillTime per step
2147:20MCCBEGIN SEQUENCE: Power on EGSEPower on EGSE1
3147:20WINDStart wind weighting analysis1
4147:20EGSECheck CLD connection1
5147:20EGSESwitch ON CLD via Battery & check voltage (24 Volt)1
6147:20EGSESwitch ON the primary and secondary supply switches on the Control Panel101:00
7146:20EGSE @MRLSwitch ON Sup_24V_20A & check voltage (ca. 27,2 Volt)1
8146:20EGSE @MRLSwitch ON Sup_24V_10A & check voltage (ca. 27,2 Volt)1
9146:20EGSE @MRLSwitch ON Sup_12V_10A & check voltage (ca. 13,8 Volt)1
10146:20EGSE @MRLSwitch ON Bat_24V_20A & check voltage (ca. 27,9 Volt)1
11146:20EGSE @MRLSwitch ON Bat_24V_10A & check voltage (ca. 27,9 Volt)1
12146:20EGSE @MRLSwitch ON Bat_12V_10A & check voltage (ca. 13,8 Volt)1
13146:20EGSE @MRLSwitch ON Sup_24V_40A1
14146:20EGSE @MRLSwitch ON Sup_5V_10A103:00
15143:20EGSEConnect to cRio1
16130:40EGSEConfirm storage capacity of cRio is greater than 300MB100:10
17143:20EGSEStart RT_VI1
18143:20EGSEOpen PID-VI and confirm it is running1
19143:20EGSERename PID-Logfile102:00
20141:20MCCBEGIN SEQUENCE: Connect Data UmbilicalConnect Data Umbilical100:30
21141:20MRLConfirm working personel is grounded1
22141:20EGSL @MRLConfirm ALL 8 Grounding bridges are inserted1
23141:20EGSL @MRLConnect Data Umbilical1
24140:50EGSETurn on EPS_BAT1
25140:50EGSETurn on EPS_EXT1
26140:50EGSE @MRLLeave EPS_BAT inserted and remove the other 7 Grounding Bridges1
27140:50EGSE @MRLInsert EPS_EXT Fuse in Power Supply Control Panel1
28140:50EGSE @MRLConfirm green LED at EPS_EXT Fuse is on1
29140:50EGSE @MRLInsert Main_Bus Fuse in Power Supply Control Panel1
30140:50EGSE @MRLConfirm LED at Main_Bus Fuse is OFF. Else Pull fuse and insert all Grounding Bridges1
31140:50EGSE @MRLSet remaining Fuses (except Payload Fuse) and check for green LED1
32140:50EGSETurn OFF EPS_BAT1
33140:50EGSE @MRLConfirm Main bus LED is on.1
34140:50EGSEStart EPS via EPS_ext1
35140:50OBDHClear SD-Card-using FileZilla FTP101:00
36139:50OBDHConnect to sbRio1
37139:50OBDHStart RT_Main1
38139:50MRLConfirm 3 beeps at OBC11
39139:50OBDHOpen RT_Sub_HMI1
40139:50OBDHConfirm Main Chute button is disabled1
41139:50EGSE @MRLInsert Payload Fuse1
42139:50EGSE @MRLConfirm green LED at Payload Fuse is on1
43139:50WINDReport on weather situation1
44139:50MCCBEGIN SEQUENCE: Connect Fueling armConnect Fueling Arm1
45139:50MRLConfirm working personel is grounded101:00
46139:50MRLConfirm PPG 0 bar1
47138:50MRLRemove Pneumatic Line from Fueling arm1
48138:50MRLMove Fueling arm to rocket1
49138:50MRLCouple Helium coupling1
50138:50MRLCouple N2O coupling1
51138:50MRLReattach Pneumatic Line to Fueling arm103:00
52135:50EGSEBEGIN SEQUENCE: EGSE sensor and actuator testEGSE sensor & actuator test1
53135:50MCCConfirm that video recording is enabled @ MCC100:10
54135:50MRLConfirm that Ignition Umbilical is disconnected1
55135:40OBDHCheck EPS hardware Voltages100:10
56135:30EGSEStart PID data recording100:10
57135:20MRLClose HPNV1100:10
58135:20MRLClose HPNV2100:10
59135:10EGSE/ MRLSwitch OxDV to closed & check if magnetic valve LED is on100:10
60135:00EGSE/ MRLSwitch HPDV to closed & check if magnetic valve LED is on100:10
61134:50EGSE/ MRLCheck warning lamp on HPSM100:10
62134:40MRLRemove loose equipment103:00
63131:40EGSEActivate Heizi100:10
64131:30EGSEActivate N2O_Heater 1100:10
65131:20EGSEActivate N2O_Heater 2100:10
66131:10EGSEActivate He_Heater100:10
67131:00OBDHVerify Heizi @ RDVT & RDVET100:10
68130:50EGSE/ MRLCheck Bottle Temperatures @ OxT1, OxT2, HPT2. If above 30C aknowledge high temperature. If above 35C enter HOLD100:10
69130:40EGSE/ MRLCheck Water Temperatures @ OxWT1, OxWT2, HPWT2100:10
70130:30EGSEDeactivate Heizi100:10
71130:20EGSE/ MRLCheck OxV1 (CLD & RT_VI)100:10
72130:10EGSE/ MRLCheck OxV2 (CLD & RT_VI)100:10
73130:00EGSE/ MRLCheck MPV3 (CLD & RT_VI)100:10
74129:50EGSE/ MRLCheck HPV1 (CLD & RT_VI)100:10
75129:40EGSE/ MRLCheck HPV2 (CLD & RT_VI)100:10
76129:30EGSE/ MRLCheck MPV1/2 (CLD & RT_VI)100:10
77129:20EGSE/ MRLCheck RDV (CLD & RT_VI)100:10
78129:10EGSE/ MRLCheck RMOxOV (CLD & RT_VI)100:10
79129:00EGSE/ MRLCheck RMOxSV (CLD & RT_VI)100:10
80128:50OBDHActivate Heizi100:10
81128:40OBDHVerify Heizi @ RDVT & RDVET101:00
82127:40OBDH/ MRLCheck RDV100:10
83127:30OBDH/ MRLCheck RNCEV100:10
84127:20OBDH/ MRLCheck RMOxOV100:10
85127:10OBDH/ MRLCheck RMOxSV100:10
86127:00OBDH/ MRLDisable RNCEV100:10
87125:00MRLConfirm MBV closed1
88125:00EGSEConfirm that all valve switches are in OFF position (Except OxDV & HPDV)100:10
89115:00MRL/ EGSECheck loadcell by applying force to it100:20
90114:40OBDHCheck RHPPT shows atmosphere1
91114:40OBDHCheck ROxTPT shows atmosphere1
92114:40OBDHCheck RIHPT shows atmosphere1
93114:40OBDHCheck RCCPT shows atmosphere1
94114:40OBDHCheck RBaro1 shows atmosphere1
95114:40OBDHCheck RBaro2 shows atmosphere1
96114:40EGSECheck HPPT1 shows 0 bar100:20
97114:20EGSECheck HPPT2 shows 0 bar1
98114:20EGSECheck HPLPT shows 0 bar1
99114:20EGSECheck OxInPT1 shows 0 bar1
100114:20EGSECheck OxInPT2 shows 0 bar1
101114:20EGSECheck OxOutPT shows 0 bar100:20
102114:00EGSE/ MRLSwitch on N2O coupling & check if magnetic valve LED is on1
103114:00EGSE/ MRLSwitch on He coupling & check if magnetic valve LED is on1
104114:00EGSE/ MRLSwitch on swivle arm & check if magnetic valve LED is on1
105114:00EGSESwitch off swivel arm & He coupling & N2O coupling101:00
106114:00MCCBEGIN SEQUENCE: Ignition signal TestIgnition signal Test101:00
107113:00MRLConfirm that Ignition Umbilical is disconnected1
108113:00MRLConnect Ignition test receptical1
109113:00EGSE @MRLPlug in Bridges B1 and B21
110113:00MRLConfirm Soundsignal from Ignition Umbilical1
111113:00EGSETurn on Ignition Secure Switch1
112113:00EGSE/ OBDHTurn on Ignition Switch for 2 Second & Confirm ignition signal received at sbRio & cRio1
113113:00EGSEConfirm that Ignition Switch is switched OFF and secured1
114113:00EGSETurn off Ignition Secure Switch1
115113:00EGSE @MRLRemove Bridges B1 and B21
116113:00MRLRemove Ignition test receptical103:00
117110:00MCCBEGIN SEQUENCE: Ground segment pressure test (PHASE YELLOW) GSE Pressure Test2LuF, AlS, LeD: 1x Helm, 3x Ear protectorsChB, FiH, JuL, LiA, MiS
118130:50EGSE/ MRLCheck Bottle Temperatures @ OxT1, OxT2, HPT2. If above 30C aknowledge high temperature. If above 35C enter HOLD200:10
119130:40EGSE/ MRLCheck Water Temperatures @ OxWT1, OxWT2, HPWT2200:10
120110:00MRLConfirm that all hatches are closed201:00
121109:00MRLConfirm He bottle 1 connector is attached2
122109:00MRLConfirm He bottle 2 connector is attached2
123109:00MRLConfirm N2O bottle 1 connector is attached2
124109:00MRLConfirm N2O bottle 2 connector is attached2
125109:00MRLConfirm hose between HPSM & N2OSM is connected on both ends2
126109:00MRLConfirm hose between HPSM & Flight Segment is connected on both ends2
127109:00MRLConfirm hose between N2OSM & Flight Segment is connected on both ends2
128109:00MRLConfirm pneumatic hose is connected on both ends202:00
129107:00MRLPut on safety equipment2
130107:00MRLConfirm MBV is closed2
131107:00MRLConfirm HPNV1 is closed2
132107:00MRLConfirm HPNV2 is closed2
133107:00MRLTake positions to open He Bottle 12
134107:00EGSEConfirm HPV1 is closed2
135107:00EGSEConfirm MPV1/2 is closed2
136107:00MRLOpen He Bottle 1201:00
137106:00MRLCheck & compare pressure HPPT1 with HPPG1 (max 300 bar)2
138106:00MRLCheck Gastech Silver HPPR1 (max 300 to 50 bar)2
139106:00MRLCheck Harris PPR (50 to 8 bar)2
140106:00MRLCheck pneumatic PPG (8 bar)2
141106:00MRLStep back201:00
142105:00EGSE/ MRLOpen & Close HPV1 SHORTLY & Check HPPT12
143105:00EGSECheck HPPT1 300 Bar2
144105:00EGSEConfirm HPLPT 0 Bar2
145105:00EGSE/ MRLOpen & Close HPV2 SHORTLY & Confirm HPPT2 0 bar2
146105:00EGSE/ MRLOpen & Close HPDV SHORTLY & Confirm HPLPT 0 bar2
147105:00EGSE/ MRLOpen & Close OxV1 SHORTLY2
148105:00EGSE/ MRLOpen & Close OxV2 SHORTLY2
149105:00EGSE/ MRLOpen & Close OxDV SHORTLY2
150105:00EGSE/ MRLOpen & Close MPV3 SHORTLY2
1510:00MRLOpen HPNV1 completely2
1520:00MRLStep Back2
1530:00EGSEOpen & Close HPV1 STEPWISE untile HPLPT equal to HPPT1 and check for leakage @HPLPT (If leakage occurs continue with "GSE Passivation Procedure")2
1540:00EGSEConfirm RHPPT & RoxTPT 1 Bar (on Pressure continue with "Rocket Passivation Procedure")2
1550:00EGSEOpen HPV12
1560:00EGSEOpen & Close HPV2 STEPWISE untile HPPT2 equal to HPLPT and check for leakage @HPPT2 (If leakage occurs continue with "GSE Passivation Procedure")2
1570:00EGSEClose HPV12
1580:00EGSEOpen HPDV & confirm HPLPT 0 Bar2
1590:00EGSEOpen HPV2 & confirm HPPT2 0 Bar2
1600:00EGSEClose HPV22
1610:00EGSEClose HPDV2
16287:10EGSEOpen & Close STEPWISE MPV1/2 to 50 Bar @ OxInPT1 & OxInPT22
16387:10EGSEConfirm MPV1/2 closed2
16487:10EGSEOpen OxDV2
16587:10EGSEOpen & Close STEPWISE MPV3 to 0 Bar @OxOutPT2
16687:10EGSECheck OxInPT1 and OxInPT2 for leakage (If leakage occurs proceed to GSE passivation Procedure)2
16787:10EGSEConfirm MPV3 closed2
16887:10EGSEOpen & Close STEPWISE OxV1 to 0 Bar @OxInPT12
16987:10EGSEOpen & Close STEPWISE OxV2 to 0 Bar @OxInPT22
17087:10EGSEConfirm OxOutPT 0 Bar2
17187:10EGSEClose OxDV2
172105:00EGSEConfirm HPLPT & OxOutPT 0 Bar201:30
173103:30EGSEDecouple N2O coupling2
174103:30EGSEDecouple Helium coupling200:20
175103:10EGSEMove arm away from rocket2
176103:10EGSEMove arm to rocket201:00
177102:10MRLClose He Bottle 1 and check HPSM for leakage (If leakage occurs continue with Passivation Procedure)201:00
178101:10MRLOpen MBV2
179101:10EGSE/ MRLCheck and compare pressure HPPT1 with HPPG1 0 Bar2
180101:10MRLClose MBV200:30
181100:40MRLOpen RMDV & relief pressure2
182100:40MRLClose RMDV2
183100:40MRLSafety is ensured2
184100:40MCCEGSE @MRL to MRL1
185100:40EGSESwitch OFF N20 coupling1
186100:40EGSESwitch OFF He coupling1
187100:40MRLConfirm working personel is grounded101:00
188100:40MRLConfirm PPG 0 Bar100:20
189100:40MRLRelease Pneumatic lines of couplings100:20
190100:20EGSEConfirm Fueling arm is switched OFF1
191100:20EGSEConfirm OxOutPT and HPLPT 0 bar1
192100:20MRLCouple He coupling100:30
19399:50MRLCouple N2O coupling100:30
19499:50MRLConfirm He coupling is connected properly1
19599:50MRLConfirm N2O coupling is connected properly1
196130:50EGSE/ MRLCheck Bottle Temperatures @ OxT1, OxT2, HPT2. If above 30C aknowledge high temperature. If above 35C enter HOLD100:10
197130:40EGSE/ MRLCheck Water Temperatures @ OxWT1, OxWT2, HPWT2100:10
19899:20MRLHOLDHOLD1
19999:20MCCCONTINUE AFTER HOLD1
200130:50EGSE/ MRLCheck Bottle Temperatures @ OxT1, OxT2, HPT2. If above 30C aknowledge high temperature. If above 35C enter HOLD100:10
201130:40EGSE/ MRLCheck Water Temperatures @ OxWT1, OxWT2, HPWT2100:10
20299:20MRLBEGIN SEQUENCE: Prime RocketPrime Rocket2
20399:20EGSETurn ON EPS_BAT201:00
20499:20MRLConfirm working personel is grounded201:00
20599:20MRLConfirm all spring retracted hatches are moving freely2
20698:50MRLTurn on GoPro Camera at end of Launch Rail200:20
20799:20MRLConnect Ignition Umbilical200:30
20898:30MRLInsert all EPS Bridges203:00
20995:30MRLConfirm Bridge Hatch is Secured200:20
21095:10EGSE @MRLreturn to MCC2
21195:10OPSElevate MRL to 90 degrees205:00
21289:40EGSEZero OxTank Mass201:00
21388:40MCCBEGIN SEQUENCE: Fueling Preparations (PHASE YELLOW)Fueling Preparations2
214130:50EGSE/ MRLCheck Bottle Temperatures @ OxT1, OxT2, HPT2. If above 30C aknowledge high temperature. If above 35C enter HOLD200:10
215130:40EGSE/ MRLCheck Water Temperatures @ OxWT1, OxWT2, HPWT2200:10
216127:40OBDH!!!Check RDV200:10
217127:30OBDH!!!Check RNCEV200:10
218127:20OBDH!!!Check RMOxOV200:10
219127:10OBDH!!!Check RMOxSV200:10
220127:00OBDH!!!Disable RNCEV200:10
22188:40MRLPut on safety equipment200:30
22210:10MRLConfirm HPNV1 is Open2
22310:10MRLConfirm HPNV2 is Closed2
22488:10MRLOpen He Bottle 1201:00
22587:10MRLStep back2
2260:00EGSEOpen & Close HPV1 STEPWISE untile HPLPT equal to HPPT1 and check for leakage @HPLPT (If leakage occurs continue with "GSE Passivation Procedure")2
2270:00EGSEOpen HPV12
2280:00EGSEOpen & Close HPV2 STEPWISE untile HPPT2 equal to HPLPT and check for leakage @HPPT2 (If leakage occurs continue with "GSE Passivation Procedure")2
2290:00EGSEClose HPV12
2300:00EGSEOpen HPDV & Confirm HPLPT 0 Bar2
2310:00EGSEConfirm HPV1 is closed2
2320:00EGSEConfirm HPV2 is closed2
23310:10MRLOpen HPNV2 1/8 Rev2
2340:00EGSEClose HPDV2
23587:10EGSEOpen & Close STEPWISE MPV1/2 to 50 Bar @ OxInPT1 & OxInPT22
23687:10EGSE/ MRLCheck & compare OxInPT1 with OxInPG1 based on Bottle temperature (max 50 bar)2
23787:10EGSE/ MRLCheck & compare pressure OxInPT2 with OxInPG2 based on Bottle temperature (max 50 bar)2
23887:10EGSE/ MRLCheck Temperature of N2O Bottle 1 @OxT1 & OxWT1 (max 22C)2
23987:10EGSE/ MRLCheck Temperature of N2O Bottle 2 @OxT2 & OxWT2 (max 22C)201:30
24085:40MRLOpen He Bottle 22
24185:40EGSE/ MRLCheck & compare pressure HPPT2 with HPPG2 (max 315 bar)201:00
24284:40ALL/ MRLCAUTION!2
24384:40MRLOpen N2O Bottle 12
24484:40MRL/ EGSECheck & compare pressure OxInPT 1 with OxInPG 1 (max 50 bar)202:00
24582:40MRLOpen N2O Bottle 22
24682:40MRL/ EGSECheck & compare pressure OxInPT 2 with OxInPG 2 (max 50 bar)202:00
24780:40MRLInsert Ignition Bridges B1 and B2 into EGSE202:00
24878:40MRLConfirm Soundsignal from Ignition Umbilical2
24978:40MRLClose ComTerm & Go to Block House2
25078:40MCCTurn OFF MRL confirm lock2
25178:40ALLInform OPS to clear Launch Pad (Tel.: [!!!])202:00
252147:20WINDStart wind weighting analysis2
253130:50EGSE/ MRLCheck Bottle Temperatures @ OxT1, OxT2, HPT2. If above 30C aknowledge high temperature. If above 35C enter HOLD200:10
254130:40EGSE/ MRLCheck Water Temperatures @ OxWT1, OxWT2, HPWT2200:10
25568:40MCCHOLDHOLD2
25668:40KLPStart Camera Karsten Lapp<70>hn2
25768:40MCCCONTINUE AFTER HOLD2
258130:50EGSE/ MRLCheck Bottle Temperatures @ OxT1, OxT2, HPT2. If above 30C aknowledge high temperature. If above 35C enter HOLD200:10
259130:40EGSE/ MRLCheck Water Temperatures @ OxWT1, OxWT2, HPWT2200:10
260130:40EGSEConfirm storage capacity of CRio is greater than 300MB200:10
261127:00OBDHConfirm RNCEV is disabled200:10
26268:40MCCBEGIN SEQUENCE Ox Fueling (PHASE RED)Ox Fueling (PHASE RED)3
26368:50WINDReport on weather situation3
26468:40MCCAnnounce end of Radio Silence3
26568:40EGSETurn OFF EPS_BAT3
266126:50OBDH/ TMTCConfirm RF451-Link300:20
267126:30TMTCConfirm GPS-lock300:20
268126:10TMTCConfirm Telemega-Link300:20
269125:50OBDHTest Connection to STX3300:20
270125:30OBDHConfirm that STX3 Packages are received by email300:30
271125:30AVCTurn on main TMTC screen300:30
272125:30MCCRequest Permission to begin fueling from OPS303:00
27368:40OBDHAcknowledge start of Fueling301:00
27467:40EGSEOpen & Close HPV1 STEPWISE to 50 Bar @ ROxTPT (stop every 10 bar & check ROxTBT & ROxTTT (approx. ambiente temp)3
27567:40EGSEConfirm OxOutPT 0 Bar to check ROxCV tightness3
27667:40EGSEOpen & Close HPV1 STEPWISE to more than 50 Bar @ RHPPT and confirm ROxTPT 50 Bar3
27767:40EGSEConfirm HPV1 is closed3
27867:40OBDHOpen RDV SHORTLY, to check tightness @ RHPPT & ROxTPT (If leakages occur continue with Abort Procedure)3
27967:40EGSEOpen MPV1/23
28067:40EGSEOpen & Close MPV3 STEPWISE to 50 Bar @ OxOutPT3
28167:40EGSEClose MPV1/23
28267:40EGSECheck & compare OxOutPT with OxInPT13
28367:40EGSECheck if RHPPT & ROxTPT more than OxInPT1, If less Open & Close HPV13
28467:40EGSEZero OxTank Mass3
28567:40MCCWrite down Time3
28667:40EGSEOpen OxV1304:00
28763:40OBDHOpen & Close RDV STEPWISE until N2O bottle empty or 25kg OxTankMass, keep temperatures RDVT and RDVET above 10<31>C and Check delta ROxTPT and OxInPT1330:00:00
28833:40EGSEVerify Bottle Temperatures @ OxT1, OxT2, HPT2300:10
28933:40EGSEVerify Water Temperatures @ Ox@T1, OxWT2, HPWT2300:10
29033:40EGSEClose OxV1300:10
29133:30EGSECheck if Pressure rises in OxPT1, if Pressure rises relief via OxV1 or wait for Pressure relief valve301:00
29232:30EGSECheck & compare OxOutPT with OxInPT23
29332:30EGSECheck & compare RHPPT & ROxTPT 50 Bar and more than OxInPT2, If less Open & Close HPV13
29432:30EGSEOpen OxV2 3
29532:30OBDHOpen & Close RDV STEPWISE to 25kg OxTankMass, keep temperatures RDVT and RDVET above 10<31>C and Check delta OxTPT and OxInPT1320:00
29612:30EGSEClose OxV2 300:10
29712:20EGSECheck if Pressure rises in OxPT2, if Pressure rises relief via OxV2 or wait for Pressure relief valve301:00
29811:20EGSEOpen OxDV STEPWISE until OxOutPT 0 Bar3
29911:20OBDHCheck ROxCV for tightness @ ROxTPT3
30011:20EGSEClose OxDV301:00
30110:20EGSEWrite down OxTankMass3
30233:40EGSEVerify He Bottle 2 Temperature @HPT2 & @HPWT2 (turn ON He_Heater if necessary) 300:10
30310:20MCCProvide OxTankMass and temperature readings to Wind weighting station300:30
3049:50EGSEConfirm OxV1 & OxV2 closed3
3059:50EGSEConfirm OxOutPT 0 Bar3
3069:50EGSEDecouple N2O coupling300:20
3079:30MCCConfirm End of Oxidator Fueling to OPS300:15
3089:20WINDStart wind weighting analysis3
3099:15OBDH/ TMTCCheck RF451-Link300:20
3108:55TMTCCheck GPS-lock300:20
3118:35TMTCCheck Telemega-Link300:20
31233:40EGSEVerify He Bottle 2 Temperature @HPT2 & @HPWT2 (turn ON/OFF He_Heater if necessary) 300:10
3138:15MCCHOLD (Last possible scheduled HOLD)HOLD3
3148:15OPSAlign MRL to Launch Trajectory3
3158:15MCCTurn audio volume down3
3168:15MCCTurn OFF ComTerm step delay3
3178:15ALLTalk through Ignition Sequence3
3188:15MCCWait for OPS to confirm final MRL adjustment3
3198:15WINDReport on weather situation3
3208:15MCCCONTINUE AFTER HOLD3
3218:15AVCStart Video recording in Block House3
3228:15EGSEVerify He Bottle 2 Temperature @HPT2 & @HPWT2 (turn ON/OFF He_Heater if necessary) 300:10
3238:15MCCBEGIN SEQUENCE: Switching to Internal Power SequenceSwitch to Internal Power3
3248:15EGSETurn OFF EPS_Ext (Switch to internal Power)300:20
3257:55OBDHConfirm EPS Voltages are within limits300:10
3267:45OBDHConfirm RF451 Transmitting300:05
3277:40OBDH/ TMTCConfirm RF451-Link300:20
3287:20TMTCConfirm GPS-lock300:20
3297:00TMTCConfirm Telemega-Link300:20
3306:40OBDHSwitch to PREARMED300:10
3316:30PYLConfirm Payload is running300:20
3326:30PYLConfirm BlackBox2 is ready for launch3
3336:10AVCConfirm that videorecording @ MCC is running300:05
3346:05MCCBEGIN SEQUENCE: High Pressure FuelingHigh Pressure Fueling3
33533:40EGSEVerify He Bottle 2 Temperature @HPT2 & @HPWT2 (turn ON/OFF He_Heater if necessary) 300:10
3366:05EGSEOpen & Close HPV1 STEPWISE until RHPPT 300 Bar or pressure equal to He Bottle 13
3376:05EGSEOpen & Close HPV2 STEPWISE until RHPPT 300 Bar 3
3386:05EGSEOpen & close HPDV STEPWISE until HPLPT 0 Bar 3
3396:05EGSEConfirm HPDV closed3
3406:05OBDH/ EGSECheck for leakage & HPLPT 0 Bar & RHPPT 300 Bar 302:00
3416:05EGSETurn OFF He_Heater3
3424:05OBDHAcknowledge end of Fueling300:10
3433:55MCCConfirm End of Fueling to OPS300:20
3443:35MCCBEGIN SEQUENCE: Disconnecting Fueling ArmDisconnecting Fueling Arm300:10
3453:25EGSEConfirm HPV1 & HPV2 closed300:10
3463:15EGSEConfirm HPLPT 0 Bar 300:10
3473:05EGSEDecouple Helium coupling300:20
3482:45EGSEConfirm Helium coupling is disconnected300:10
3492:35EGSEMove fueling arm away from rocket300:40
3501:55MCCConfirm Fueling Arm away to OPS300:15
3511:40MCCPrepare for Launch300:10
3521:30OBDHConfirm ready for launch300:10
3531:20EGSEConfirm ready for launch300:10
3541:10MCCSet Go/No-Go System to Go300:10
3551:00MCCWait for Authorization for Launch300:00
3561:00MCCBEGIN SEQUENCE: IgnitionIgnition Sequence300:10
3570:50OBDHT-50 ARM300:05
3580:40OBDHT-40 Confirm all status indicators green300:05
3590:30OBDHT-30 Disconnect from sbRio300:30
3600:10EGSET-10 Turn on Ignition Secure300:07
3610:03EGSET-3: Ignition300:03
3620:00OBDHT+0: Verify RMOxOV Open (Launched)300:00
3630:00EGSET+1: Turn OFF Ignition3
3640:00EGSET+5: Turn OFF Ignition Secure3
3650:00OBDHT+20: Verify RMOxOV Closed and RMOxSV Open (Cruise)3
3660:00OBDHT+50: Verify RNCEV Open (Drogue)3
3670:00OBDHT+310: Verify Main Chute Deployed and RDV Open (Main)3
3680:00OBDHT+600: Verify (Landed)3
3690:00MCCBEGIN SEQUENCE: PASSIVATION (PHASE YELLOW)Passivation2
37068:40MCCAnnounce BEGIN of Radio Silence2
3710:00MCCTurn audio volume up2
3720:00MRLGo to MRL, Close N2O Bottle 1 & N2O Bottle 2, THEN...2
3730:00MRLRETURN to Block House2
3740:00EGSEOpen OxDV2
3750:00EGSEOpen OxV12
3760:00EGSEConfirm OxInPT1 & OxOutPT 0 Bar2
3770:00EGSEClose OxV12
3780:00EGSEOpen OxV22
3790:00EGSEConfirm OxInPT2 & OxOutPT 0 Bar2
3800:00EGSEClose OxV22
3810:00EGSEClose OxDV2
3820:00MRLGo to MRL, confirm OxInPG1 & OxInPG2 0 Bar, else RETURN to Block House, THEN...2
3830:00MRLClose He Bottle 2, THEN...2
3840:00MRLWrite down remaining Pressure of He Bottle 2, THEN...2
3850:00MRLReturn to Block House2
3860:00EGSEOpen HPDV2
3870:00EGSEOpen HPV22
3880:00EGSEConfirm pressure HPLPT & HPPT2 0 Bar2
3890:00EGSEClose HPV22
3900:00EGSEClose HPDV2
3910:00MRLGo to Testrig, confirm HPPG2 0 Bar, else return to Block House, THEN...2
3920:00MRLClose He Bottle 1, THEN ...2
3930:00MRLOpen ComTerm2
3948:15MCCTurn ON ComTerm step delay2
3950:00MRLWrite down remaining Pressure of He Bottle 12
3960:00MRLStep back2
3970:00EGSEOpen HPDV2
3980:00EGSEOpen HPV12
3990:00EGSEConfirm pressure HPLPT & HPPT1 0 Bar2
4000:00EGSEClose HPV12
4010:00EGSEClose HPDV2
4020:00EGSEPressure Check2
4030:00MRLOpen MBV2
4040:00EGSE/ MRLCheck and compare pressure HPPT1 with HPPG12
4050:00MRLClose MBV2
4060:00MRLTake out B1 & B2 Bridges2
4070:00MRLSafety is ensured2
4080:00MCCConfirm to OPS that Safety is ensured2
4090:00MCCBEGIN SEQUENCE: Data collectionData collection1
4100:00AVCTurn off GoPro & Camcorder & Stop Block House Video recording1
4110:00EGSECopy PID.vi.tdms & save to new name1
4120:00EGSEWait for buffer storage process to be finished1
4130:00EGSEsave data files from cRio to PC1
4140:00WINDSave data on external HDD1
4150:00TMTCStop TMTC Vi and save data on external HDD1
4160:00AVCEnd audio recording1
4170:00MCCStop ComTerm and save logfile to external HDD, THEN...1
4180:00MCCRestart ComTerm VI1
4190:00AVCSave video & audio data on external HDD1
4200:00MCCEND OF PROCEDUREEnd1